Compute Equity Atlas
← National map
Source-backed project record · TX

Liberty American Multi-Sourced Power and Innovation Hub (LAMP)

This record consolidates 16 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
CORROBORATEDbest evidence tier
16linked evidence rows
Project facts

Location and operating record

Operator / developerBaRupOn LLC
JurisdictionLiberty, TX
AddressNOT_FOUND (former chemical plant site)
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
Capacity3000 MW
AliasesLiberty American Multi-Sourced Power and Innovation Hub (LAMP) · LAMP campus · LAMP · BaRupOn Liberty County campus · Liberty energy campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure1 rows
SOURCE RECORD

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): source record

under_construction

Developer BaRupOn is a medical equipment manufacturer that pivoted the site. 3GW is the stated ultimate on-campus capacity target; 240MW of generation is the near-term buildout. Behind-the-meter approach chosen because grid interconnection was quoted at 2029 with ~$35M in upgrade cost.

Key data: Behind-the-meter / off-grid on-site generation (grid interconnection deferred to 2029 with ~$35M in upgrade costs) | Off-grid / behind-the-meter | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): ownership and profile

under_construction

Developer: BaRupOn LLC | Owner: BaRupOn LLC | County: Liberty | Research region: Houston / Gulf Coast

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): power and grid

under_construction

Key data: Utility: Behind-the-meter / off-grid on-site generation (grid interconnection deferred to 2029 with ~$35M in upgrade costs) | Utility region: Behind-the-meter; Entergy Texas territory | Grid area: Off-grid / behind-the-meter | Gross MW: 3000 | Onsite generation MW: 240

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): water and cooling

under_construction

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): permits and jurisdiction

under_construction

Key data: Jurisdictions: Liberty County | TCEQ | ERCOT/PUCT (deferred interconnection)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): civic and community

under_construction

Change.org petition opposing the AI data center in Liberty County

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): environment and site

under_construction

Brownfield reuse of a former chemical plant

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Multi-source generation strategy: natural gas, geothermal, solar and planned advanced nuclear

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: 4.5M sq ft of planned innovation/manufacturing space co-located with the compute campus

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): timeline

under_construction

Groundbreaking on the 701-acre former chemical plant site

Claim classification: Not yet assigned

Status date: 2025-01

Open source 1 →

under_construction

Coverage of off-grid power strategy: natural gas plus geothermal, solar and planned advanced nuclear

Claim classification: Not yet assigned

Status date: 2026

Open source 1 →

under_construction

Spectrum News covers the Liberty County energy campus

Claim classification: Not yet assigned

Status date: 2026-05-01

Open source 1 →

CAPACITY GROSS POWER

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): capacity gross power

under_construction

BaRupOn LLC broke ground in January 2025 on a 701-acre former chemical plant site in Liberty County for a campus planned at 3GW of total on-campus capacity with 240MW of initial generation and 4.5M sq ft of innovation/manufacturing space.

Key data: 701 acres; 3GW planned; 240MW initial generation; 4.5M sq ft

Claim classification: COMPANY_CLAIM · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2025-01

Open source 1 →

ONSITE GENERATION

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): onsite generation

under_construction

The campus is being built behind the meter using natural gas plus geothermal, solar and planned advanced nuclear, because grid interconnection was quoted with a 2029 wait and roughly $35 million in upgrade costs.

Key data: Behind-the-meter; 2029 grid wait; ~$35,000,000 upgrade cost

Claim classification: REPORTED_FACT · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2026

Open source 1 →

PROJECT STATUS

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): project status

under_construction

Spectrum News covered the Liberty County energy campus in May 2026, and KHOU/Houston Business Journal reported a California manufacturer's pivot into a Liberty County data center campus.

Key data: Liberty County energy campus under development

Claim classification: REPORTED_FACT · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2026-05-01

Open source 1 →

COMMUNITY RESPONSE

Liberty American Multi-Sourced Power and Innovation Hub (LAMP): community response

opposed

A Change.org petition titled 'Stop the AI Data Center in Liberty County, Texas' represents organized local opposition to the campus.

Key data: Change.org petition opposing the Liberty County AI data center

Claim classification: ADVOCACY_SOURCE · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2026

Limitation: Petition platform; signature counts and organizers not independently verified.

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Liberty American Multi-Sourced Power and Innovation Hub (LAMP) Data Center Project | Liberty | Compute Equity Atlas