LOGIX Katy Data Center / EdgeConneX HOU01

This record consolidates 10 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
SOURCE_BACKEDbest evidence tier
10linked evidence rows
Project facts

Location and operating record

Operator / developerLOGIX Fiber Networks; EdgeConneX
JurisdictionKaty, TX
Address1510 PrimeWest Parkway
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesLOGIX Katy Data Center / EdgeConneX HOU01 · PrimeWest Parkway · EdgeConneX HOU01 · LOGIX Katy · Federal Land Bank
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

LOGIX Katy Data Center / EdgeConneX HOU01: source record

operational

LOGIX and EdgeConneX both market space at this address; treated as one physical facility with shared occupancy.

Key data: CenterPoint Energy (Houston Electric service territory) | ERCOT | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

LOGIX Katy Data Center / EdgeConneX HOU01: ownership and profile

operational

Developer: EdgeConneX | Owner: EdgeConneX | County: Harris | Research region: Houston / Gulf Coast | Tenants/customers: AT&T | Cloudflare | Cogent | Comcast | Consolidated Communications | Crown Castle | EdgeCast | EnTouch | Grande Communications | Houston-IX | Logix | Lumen | NinjaIX | Phonoscope | PS Lightwave | Teleflex | Whitesky | Zayo | Megaport (cloud access)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

LOGIX Katy Data Center / EdgeConneX HOU01: power and grid

operational

Key data: Utility: CenterPoint Energy (Houston Electric service territory) | Utility region: ERCOT Houston (Coast) load zone | Grid area: ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

LOGIX Katy Data Center / EdgeConneX HOU01: water and cooling

operational

Key data: Cooling: 30-inch raised-floor forced-air plenum with N+1 CRAC units in separate suites

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

LOGIX Katy Data Center / EdgeConneX HOU01: permits and jurisdiction

operational

Key data: Jurisdictions: Harris County | City of Katy

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

LOGIX Katy Data Center / EdgeConneX HOU01: environment and site

operational

Key data: Surrounding infrastructure: LOGIX Fiber Networks metro fiber

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

EXACT LOCATION

LOGIX Katy Data Center / EdgeConneX HOU01: exact location

operational

LOGIX and EdgeConneX both market a 100,000 sq ft data center on 6 acres at 1510 PrimeWest Parkway, Katy 77449.

Key data: 1510 PrimeWest Pkwy, Katy 77449; 100,000 sq ft on 6 acres

Claim classification: COMPANY_CLAIM · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2026-09-05

Open source 1 →

BUILDING SQFT

LOGIX Katy Data Center / EdgeConneX HOU01: building sqft

operational

EdgeConneX documents HOU-01 as a 91,400 sq ft facility with 17,700 sq ft of raised floor for tenant racks, supporting up to 30 kW per rack, located within 30 miles of downtown Houston.

Key data: 91,400 sq ft; 17,700 sq ft raised floor; 30 kW/rack

Claim classification: COMPANY_CLAIM · Verification: PRIMARY_SOURCE · Retrieved: 2026-09-05

Status date: 2026-09-05

Limitation: CONFLICT: LOGIX markets a 100,000 sq ft building on 6 acres at 1510 PrimeWest Pkwy; EdgeConneX does not publish the street address.

Open source 1 →

FIBER NETWORK

LOGIX Katy Data Center / EdgeConneX HOU01: fiber network

operational

EdgeConneX lists 19 on-net providers at HOU-01 including AT&T, Cloudflare, Cogent, Comcast, Crown Castle, Houston-IX, Logix, Lumen, Phonoscope, PS Lightwave and Zayo, with cloud access via Megaport and diverse building points of entry to physically diverse meet-me rooms.

Key data: 19 on-net providers; Megaport cloud access; diverse POEs/MMRs

Claim classification: COMPANY_CLAIM · Verification: PRIMARY_SOURCE · Retrieved: 2026-09-05

Status date: 2026-09-05

Open source 1 →

COOLING TECHNOLOGY

LOGIX Katy Data Center / EdgeConneX HOU01: cooling technology

operational

The facility uses a 30-inch raised/under-floor forced-air plenum with N+1 CRAC units located in separate suites, and holds HIPAA, PCI-DSS, SOC 2 Type 2 and ISO 27001 compliance.

Key data: 30-inch plenum; N+1 CRACs; SOC 2 Type 2 / ISO 27001

Claim classification: COMPANY_CLAIM · Verification: PRIMARY_SOURCE · Retrieved: 2026-09-05

Status date: 2026-09-05

Open source 1 →