Source-backed project record · TX

Longhorn Data Center

This canonical record consolidates 12 source-backed observations without discarding aliases, limitations or unresolved dimensions.

operationalproject status
VERIFIED_PRIMARYbest evidence tier
12linked evidence rows
Project facts

Location and operating record

Operator / developerCrusoe operates; OpenAI primary customer; Oracle manages AI infrastructure
JurisdictionTaylor County / Abilene, TX
AddressNot published
Location precisionexact coordinate
Coordinates32.50792, -99.77722
Capacity1200 MW
AliasesLonghorn Data Center (Crusoe)
Evidence coverage

What has been researched

Project profile9 rows
Intent / permits1 rows
Civic / infrastructure2 rows
EXACT LOCATION

Longhorn Data Center: exact location

CORROBORATED

Facility coordinates published for the Longhorn power station serving the Abilene campus

Key data: Latitude 32.50792, longitude -99.77722

Limitation: Street address and parcel not published; site is on the Lancium Clean Campus, roughly 1,100 acres

Open source →

OWNERSHIP CHAIN

Longhorn Data Center: ownership chain

CORROBORATED

Owners of record listed as a campus master association and Crusoe's operating entity

Key data: "Abilene Data Center Campus Master Association" (Unit 1) and Crusoe Energy Systems LLC

Limitation: Underlying land is the Lancium Clean Campus; the Taylor County appraisal-district deed chain was not retrieved

Open source →

OPERATOR

Longhorn Data Center: operator

VERIFIED_PRIMARY

Crusoe builds and operates the campus; OpenAI is the primary customer and Oracle manages the AI infrastructure layer

Key data: Crusoe operates; OpenAI primary customer; Oracle manages AI infrastructure

Limitation: Tenant-by-building allocation not disclosed

Open source →

POWER SUPPLIER

Longhorn Data Center: power supplier

VERIFIED_PRIMARY

Campus is on the Lancium Clean Campus with a large ERCOT interconnection; Crusoe announced expansion to 1.2 GW

Key data: 1.2 gigawatt ERCOT interconnection at the Lancium Clean Campus

Limitation: No specific ERCOT interconnection agreement number or transmission service provider name was published

Open source →

WATER SUPPLIER

Longhorn Data Center: water supplier

VERIFIED_PRIMARY

Project site states cooling is closed-loop with municipal water for makeup and sanitary discharge to city sewer

Key data: Municipal water supply; roughly 50,000 gallons per year per building; wastewater to sanitary sewer

Limitation: "Municipal water supply" is not named as City of Abilene by the source and no water service agreement is referenced

Open source →

JURISDICTION STACK

Longhorn Data Center: jurisdiction stack

CORROBORATED

State air/water permitting via TCEQ, county is Taylor, economic development runs through the city's development corporation

Key data: Development Corporation of Abilene (DCOA) as the local development entity

Limitation: No MUD/PID or groundwater conservation district identified for this site

Open source →

ECON DEV CONTACT

Longhorn Data Center: econ dev contact

VERIFIED_PRIMARY

Crusoe's release names the DCOA chief executive as the local economic-development principal

Key data: Misty Mayo, President and CEO, Development Corporation of Abilene; developabilene.com

Limitation: Direct phone/email not published in the release

Open source →

SURROUNDING INFRASTRUCTURE

Longhorn Data Center: surrounding infrastructure

VERIFIED_PRIMARY

Site sits inside the Lancium Clean Campus, a purpose-built power-adjacent campus in the ERCOT West zone

Key data: Lancium Abilene Clean Campus hosting the Crusoe buildings

Limitation: Specific substation names, line voltages, water mains, rail and fiber carriers not stated

Open source →

PLANNING ZONING CONTACT

Longhorn Data Center: planning zoning contact

DISCOVERY_LEAD

NOT_FOUND — searched Crusoe, Lancium and project pages; no Abilene or Taylor County planning case number, department or named planner published

Limitation: Site may be outside city limits in unincorporated Taylor County, where no zoning case would exist

Open source →

AIR PERMIT APPLICATION

Longhorn Data Center: air permit application

"Pending" (on TCEQ pending NSR applications report)

Status date: Received 11/07/2025

Limitation: Location and capacity not stated on the pending-applications report.

Open source →

WATER WITHDRAWAL VOLUME

Longhorn Data Center: water withdrawal volume

Disclosed

Crusoe's own disclosure for the Abilene campus: each of eight buildings needs a 1,000,000-gallon initial fill from the municipal supply, then ~50,000 gal/building/year for maintenance; heat rejection is via air-cooled chillers with no consumptive water use.

Key data: 1,000,000 gal initial fill/building (8,000,000 gal total); ~50,000 gal/building/yr

Status date: 2026 (page current)

Limitation: Company self-report; no TCEQ or City of Abilene water permit document located this session. (confidence detail: VERIFIED_PRIMARY (company disclosure))

Open source →

FISCAL IMPACT LOCAL GOVERNMENT

Longhorn Data Center: fiscal impact local government

Disclosed

Crusoe/Development Corporation of Abilene project ~**$1 billion** in direct and indirect economic impact over 20 years from the first two buildings, and say the fully operational campus would equal up to **32% of Abilene's FY2025 budgeted property tax revenue** and **25% of Taylor County's**.

Key data: ~$1B 20-yr impact; up to 32% of city and 25% of county FY2025 budgeted property tax revenue

Status date: 2026 (page current)

Limitation: Company/EDC projection, not an audited fiscal-impact study; abatement terms not disclosed on the page.

Open source →

Sources

Evidence and provenance

  • Global Energy Monitor (GEM.wiki) · CORROBORATED
    Limitation: Street address and parcel not published; site is on the Lancium Clean Campus, roughly 1,100 acres
  • Crusoe / Abilene AI Data Center project site · VERIFIED PRIMARY
    Limitation: Tenant-by-building allocation not disclosed
  • Crusoe · VERIFIED PRIMARY
    Limitation: No specific ERCOT interconnection agreement number or transmission service provider name was published
  • Lancium · VERIFIED PRIMARY
    Limitation: Specific substation names, line voltages, water mains, rail and fiber carriers not stated
  • TCEQ · VERIFIED PRIMARY
    Limitation: Location and capacity not stated on the pending-applications report.
  • Crusoe Energy Systems · VERIFIED PRIMARY
    Limitation: Company self-report; no TCEQ or City of Abilene water permit document located this session. (confidence detail: VERIFIED_PRIMARY (company disclosure))

Open TX state research →