Meta Fort Worth Data Center

This record consolidates 14 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
CORROBORATEDbest evidence tier
14linked evidence rows
Project facts

Location and operating record

Operator / developerMeta Platforms, Inc.
JurisdictionFort Worth, TX
AddressNot published
Location precisionlocality centroid
Coordinates32.781954, -97.348573
CapacityNot established
AliasesMeta Fort Worth Data Center · Meta Fort Worth Campus · Facebook Fort Worth Data Center
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Meta Fort Worth Data Center: source record

operational

Five data center buildings totaling ~2.5M sq ft on ~170 acres. Largest operational data center campus in Fort Worth.

Key data: Oncor Electric Delivery (assumed service territory; not confirmed in fetched sources) | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Meta Fort Worth Data Center: ownership and profile

operational

Developer: Meta Platforms, Inc. (general contractor DPR Construction) | Owner: Meta Platforms, Inc. | County: Tarrant | Research region: Dallas-Fort Worth / North Texas

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Meta Fort Worth Data Center: power and grid

operational

Key data: Utility: Oncor Electric Delivery (assumed service territory; not confirmed in fetched sources) | Grid area: ERCOT | Substations: Dedicated on-site substation serving the campus

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Meta Fort Worth Data Center: water and cooling

operational

Key data: Water demand: reported ~75% less water than comparable data centers | Cooling: Meta rapid-deploy design with outdoor-air/evaporative cooling (per developer description)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Meta Fort Worth Data Center: permits and jurisdiction

operational

Key data: Jurisdictions: City of Fort Worth | Tarrant County | State of Texas | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Meta Fort Worth Data Center: environment and site

operational

Key data: Surrounding infrastructure: Own on-site substation

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

operational

Key data: Surrounding infrastructure: North Fort Worth industrial corridor

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Meta Fort Worth Data Center: timeline

operational

Groundbreaking on Fort Worth campus

Claim classification: Not yet assigned

Status date: 2015

Open source 1 →

operational

Fifth and final building completed; campus complete

Claim classification: Not yet assigned

Status date: 2023

Open source 1 →

CAMPUS ACRES

Meta Fort Worth Data Center: campus acres

operational

Meta's Fort Worth campus comprises five data center buildings on about 170 acres.

Key data: 170 acres; 5 buildings; ~2.5M sq ft

Claim classification: REPORTED_FACT · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2023

Open source 1 →

BUILDING SQFT

Meta Fort Worth Data Center: building sqft

operational

The completed Meta Fort Worth campus totals approximately 2.5 million square feet.

Key data: 2,500,000 sq ft

Claim classification: REPORTED_FACT · Verification: CORROBORATED · Retrieved: 2026-09-05

Status date: 2023

Open source 1 →

JOBS

Meta Fort Worth Data Center: jobs

operational

Construction peaked at roughly 1,200 workers, with 200+ permanent operations jobs.

Key data: 1,200 construction workers; 200+ permanent jobs

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2023

Open source 1 →

SUBSTATION

Meta Fort Worth Data Center: substation

operational

The campus is served by its own dedicated substation.

Key data: dedicated on-site substation

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2023

Open source 1 →

WATER DEMAND

Meta Fort Worth Data Center: water demand

operational

Meta reports the Fort Worth facility uses roughly 75% less water than comparable data centers.

Key data: ~75% less water than comparable facilities

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2023

Limitation: Developer-reported figure, not an independent measurement.

Open source 1 →