Metrobloks Liberty Data Center Campus

This record consolidates 7 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
CORROBORATEDbest evidence tier
7linked evidence rows
Project facts

Location and operating record

Operator / developerMetrobloks
JurisdictionLiberty, MO
Address2515 Old Hughes Rd
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesMetrobloks Liberty Data Center Campus · Metrobloks Liberty
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Metrobloks Liberty Data Center Campus: source record

announced

Three buildings, 30 permanent jobs at $95,649 average wage per Missouri DED. Capacity conflict: servercountry.org lists 150 MW; Metrobloks' own MCI-A site page (2505 Old Hughes Rd, two buildings) lists 111 MW critical IT capacity within a 150 MW envelope. Possible duplicate of TEMP-7 (MCI-A) - adjacent addresses on the same road, same operator; retained separately because building counts and square footage differ.

Key data: Evergy | SPP (Evergy Metro)

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

OWNERSHIP AND PROFILE

Metrobloks Liberty Data Center Campus: ownership and profile

announced

Developer: Metrobloks | County: Clay | Research region: Kansas City Northland

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

POWER AND GRID

Metrobloks Liberty Data Center Campus: power and grid

announced

Key data: Utility: Evergy | Grid area: SPP (Evergy Metro)

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

WATER AND COOLING

Metrobloks Liberty Data Center Campus: water and cooling

announced

Key data: Cooling: Design described as very low water use

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

PERMITS AND JURISDICTION

Metrobloks Liberty Data Center Campus: permits and jurisdiction

announced

Key data: Jurisdictions: Liberty | Clay County | Missouri | Tax incentives: Missouri Data Center Sales Tax Exemption Program

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

TIMELINE

Metrobloks Liberty Data Center Campus: timeline

announced

Metrobloks announced a $1.4 billion, three-building, 568,800 sq ft campus in Liberty

Claim classification: Not yet assigned

Status date: 2026-03-24

Open source 1

ECONOMIC AND TAX

Metrobloks Liberty Data Center Campus: economic and tax

announced

Missouri DED announced Metrobloks would invest $1.4 billion in Liberty in a 568,800 sq ft, three-building high-density campus on about 29 acres with at least 30 jobs at an average wage of $95,649, supported by the Data Center Sales Tax Exemption Program, with Evergy named as a partner and a very low water use design.

Key data: $1.4B; 568,800 sq ft; 30 jobs at $95,649 average

Claim classification: proposal_or_announced_commitment · Verification: verified_by_primary_source · Retrieved: 2026-09-13

Status date: 2026-03-24

Limitation: State announcement of a commitment; no MW figure disclosed.