planned
Metrobloks' own site page: 111 MW total critical IT capacity, 150 MW total power envelope (24 MW committed by Evergy letter plus a 126 MW additional envelope), 70,000 sq ft whitespace, 400 W/sq ft, two buildings on two floors, N+1 UPS, 3,000 kW diesel standby generators (N+1), Uptime Tier III. Water use not stated. servercountry.org lists 'Metrobloks MCI-A Kansas City' at $1.4B / 87 MW - conflicting with the 111 MW company figure. Possible duplicate of TEMP-6.
Key data: Evergy | SPP (Evergy Metro)
Claim classification: Not yet assigned
Status date: 2026-09-13