Source-backed project record · TX

Nexus Hubbard Data Center Campus

This record consolidates 17 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
CORROBORATEDbest evidence tier
17linked evidence rows
Project facts

Location and operating record

Operator / developerNexus Data Centers
JurisdictionHubbard, TX
AddressBetween Highway 171 and County Road 3369, outside Hubbard
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesNexus Hubbard Data Center Campus · Hubbard campus between Highway 171 and County Road 3369 · Nexus Hubbard · Anthropic Hubbard campus · Waco-area Anthropic campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure2 rows
SOURCE RECORD

Nexus Hubbard Data Center Campus: source record

under_construction

The Axios/WSJ 'campus near Waco with its own 1.6 GW gas plant' and the Nexus Hubbard campus are matched here on capacity, developer and geography; the two reports do not explicitly state they are the same site, so treat the linkage as a strong inference. Anthropic plans to deploy Google/Broadcom-co-designed TPUs at the Hubbard site.

Key data: NOT_FOUND | ERCOT | City of Hubbard (treated effluent) | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Nexus Hubbard Data Center Campus: ownership and profile

under_construction

Developer: Nexus Data Centers | Owner: Nexus Data Centers | Permit applicant: Nexus (reinvestment zone and TCEQ power plant permits) | County: Hill | Research region: Temple-Killeen-Waco / Bryan-College Station / Texoma | Tenants/customers: Anthropic (signed leases; four Anthropic data center leases covered by the financing package) | Google (expected ~20% equity in the data center and power project in exchange for backstopping Anthropic's obligations)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Nexus Hubbard Data Center Campus: power and grid

under_construction

Key data: Utility region: ERCOT | Grid area: ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Nexus Hubbard Data Center Campus: water and cooling

under_construction

Key data: Water utility: City of Hubbard (treated effluent) | Water source: Primarily captured rainwater (~2 billion gallons/year via retention ponds); up to 100,000 gallons/day of treated effluent from the Hubbard wastewater plant; backup groundwater well approved by the Prairielands Groundwater Conservation District | Water demand: ~2 billion gallons/year rainwater capture target; up to 100,000 gpd effluent | Wastewater: Treated effluent purchased from the Hubbard wastewater treatment plant

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Nexus Hubbard Data Center Campus: permits and jurisdiction

under_construction

Key data: Permit IDs: TCEQ air permits received for the on-site power plant (per local reporting),Prairielands Groundwater Conservation District backup well approval | TCEQ air permits received for the on-site power plant (per local reporting) | Prairielands Groundwater Conservation District backup well approval | Jurisdictions: State of Texas | Hill County | City of Hubbard | Prairielands Groundwater Conservation District | TCEQ | ERCOT | Tax incentives: [object Object],[object Object] | {"agreement_name":"Hill County reinvestment zone for the Hubbard data center","agreement_number":"NOT_FOUND","approval_date":"2026-02-10","estimated_value":"Reinvestment zone approved; Nexus later withdrew its abatement/PILOT request","government_entity":"Hill County Commissioners Court","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://lakelander.com/2026/02/19/commissioners-approve-hubbard-data-center-reinvestment-zone/","term":"NOT_FOUND"} | {"agreement_name":"Withdrawn 10-year PILOT / county tax abatement negotiation","agreement_number":"NOT_FOUND","approval_date":"2026-04-07 (withdrawal announced)","estimated_value":"Withdrawn","government_entity":"Hill County Commissioners Court","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://lakelander.com/2026/04/17/nexus-pulls-out-of-county-tax-abatement-negotiations/","term":"10-year PILOT sought"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Nexus Hubbard Data Center Campus: civic and community

under_construction

Noise limited to 65 dB per project commitments

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Abatement withdrawal removed a contested county incentive

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Nexus Hubbard Data Center Campus: environment and site

under_construction

Rainwater-first water strategy with retention ponds

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

On-site gas generation permitted by TCEQ

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Backup groundwater well permitted

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Rural Hill County site near Hubbard, roughly 30 miles from Waco

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Hubbard municipal wastewater plant supplies effluent

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Nexus Hubbard Data Center Campus: timeline

under_construction

Site preparation underway

Claim classification: Not yet assigned

Status date: 2025-11

Open source 1 →

under_construction

Hill County approves a reinvestment zone for the campus

Claim classification: Not yet assigned

Status date: 2026-02-10

Open source 1 →

under_construction

Nexus withdraws from county tax abatement / PILOT negotiations

Claim classification: Not yet assigned

Status date: 2026-04-07

Open source 1 →

under_construction

Reported $15B financing led by Morgan Stanley with Google backstop and Anthropic leases

Claim classification: Not yet assigned

Status date: 2026-08-02

Open source 1 →

under_construction

Axios reports Anthropic signed leases for a Waco-area campus paired with its own 1.6 GW gas plant

Claim classification: Not yet assigned

Status date: 2026-08-26

Open source 1 →