Compute Equity Atlas
← National map
Source-backed project record · TX

Old Ocean Data Center

This record consolidates 13 research observations while retaining source distinctions, location precision and unresolved fields.

unknownproject status
CORROBORATEDbest evidence tier
13linked evidence rows
Project facts

Location and operating record

Operator / developerNightpeak Energy
JurisdictionSweeny (Old Ocean, unincorporated), TX
AddressNOT_FOUND
Location precisionparcel or bounded site
CoordinatesNot published; no coordinate inferred
Capacity620 MW
AliasesOld Ocean Data Center · Old Ocean / Sweeny site · Nightpeak Old Ocean · Bulldog Power project
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure3 rows
SOURCE RECORD

Old Ocean Data Center: source record

suspended

Configuration: two 310MW AI data centers paired with two 310MW gas turbine plants. Status recorded as 'suspended' because the tax abatements were denied and no subsequent county filing has appeared; the developer has not publicly announced cancellation.

Key data: Texas-New Mexico Power (adjacent substation); on-site gas generation via Bulldog Power | ERCOT | City of Sweeny municipal water system

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

OWNERSHIP AND PROFILE

Old Ocean Data Center: ownership and profile

suspended

Developer: Nightpeak Energy | Owner: Nightpeak Energy | Property entity: Bulldog Power (Nightpeak Energy subsidiary, generation entity) | County: Brazoria | Research region: Houston / Gulf Coast

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

POWER AND GRID

Old Ocean Data Center: power and grid

suspended

Key data: Utility: Texas-New Mexico Power (adjacent substation); on-site gas generation via Bulldog Power | Utility region: ERCOT Houston (Coast) load zone | Grid area: ERCOT | Gross MW: 620 | Onsite generation MW: 620 | Substations: Adjacent Texas-New Mexico Power substation

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

WATER AND COOLING

Old Ocean Data Center: water and cooling

suspended

Key data: Water utility: City of Sweeny municipal water system | Water source: City of Sweeny wells (3 wells, 1 reported offline)

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

PERMITS AND JURISDICTION

Old Ocean Data Center: permits and jurisdiction

suspended

Key data: Jurisdictions: Brazoria County | City of Sweeny (adjacent) | TCEQ (air permitting for gas turbines) | ERCOT/PUCT | Tax incentives: [object Object] | {"agreement_name":"Four requested Chapter 312 tax abatement agreements (100% abatement, 10-year term)","agreement_number":"NOT_FOUND","approval_date":"DENIED 2026-03-10","estimated_value":"NOT_FOUND","government_entity":"Brazoria County Commissioners Court","investment_commitment":"~$3,000,000,000-$3,500,000,000","jobs_commitment":"20 permanent jobs","source_url":"https://therealdeal.com/texas/2026/03/13/brazoria-county-rejects-tax-break-for-3-5b-data-center/","term":"10 years (requested)"}

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

CIVIC AND COMMUNITY

Old Ocean Data Center: civic and community

suspended

Residents raised concerns that Sweeny's three municipal water wells (one reportedly offline) could not support the project

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

suspended

Commissioners Court unanimously (5-0) rejected all four abatement requests on March 10, 2026

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

suspended

Brazoria County subsequently adopted a countywide resolution (June 9, 2026) stating that no future data center should proceed without an independent impact assessment

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

ENVIRONMENT AND SITE

Old Ocean Data Center: environment and site

suspended

Two 310MW natural gas turbine plants proposed on site, in an area already heavy with petrochemical emissions

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

TIMELINE

Old Ocean Data Center: timeline

suspended

Project publicized; community pushback over water and power in Brazoria County

Claim classification: Not yet assigned

Status date: 2026-02

Open source 1 →

suspended

Brazoria County Commissioners Court votes 5-0 to deny four requested 100% / 10-year tax abatements

Claim classification: Not yet assigned

Status date: 2026-03-10

Open source 1 →

suspended

Public Citizen applauds Brazoria County's rejection of the abatement

Claim classification: Not yet assigned

Status date: 2026-03

Open source 1 →

suspended

Brazoria County Commissioners Court adopts a countywide resolution on data center development; texasaidocket notes no data center abatement or reinvestment zone matter has returned to the court since

Claim classification: Not yet assigned

Status date: 2026-06-09

Open source 1 →

Sources

Evidence and provenance

Open TX state research →