operational
A January 2024 TDLR filing covers approximately $400,000 of data center upgrades at 501 Houston Avenue, Port Arthur 77641 across 1,860 sq ft, including a 750kW / 937kVA natural gas emergency generator, with work scheduled February through August 2024.
Key data: 750kW / 937kVA natural gas generator; 1,860 sq ft; ~$400,000
Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05
Status date: 2024-01-30
Limitation: Notable as a natural-gas rather than diesel emergency generator, consistent with Gulf Coast industrial gas availability.