Compute Equity Atlas
← National map
Source-backed project record · TX

Sabey Data Centers SDC Austin Campus (Round Rock)

This record consolidates 13 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
VERIFIED_PRIMARYbest evidence tier
13linked evidence rows
Project facts

Location and operating record

Operator / developerSabey Data Center Properties LLC / SDC - Austin LLC
JurisdictionRound Rock, TX
Address1300 Louis Henna Blvd
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity84 MW
AliasesSabey Data Centers SDC Austin Campus (Round Rock) · 1300 Louis Henna Boulevard · SDC Austin · SDC - Austin Tandem Data Center · SDC Austin III / SDC Austin IV · former Sears call center site
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure1 rows
SOURCE RECORD

Sabey Data Centers SDC Austin Campus (Round Rock): source record

operational

One of the very few Central Texas sites with a municipally verified water-use figure. Building A hosts TACC's Horizon system. Comptroller registrations confirm two separate registered projects (Tandem and SDC Austin III/IV) in the Sabey Austin/Round Rock portfolio.

Key data: NOT_FOUND | ERCOT South Central / Austin-Central Texas load zone | City of Round Rock Water | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Sabey Data Centers SDC Austin Campus (Round Rock): ownership and profile

operational

Developer: Sabey Data Centers | Owner: SDC - Austin LLC; SDC Austin III LLC | Property entity: SDC - Austin LLC / SDC Austin III LLC | County: Williamson | Research region: Austin / Central Texas | Tenants/customers: Texas Advanced Computing Center (TACC) — Horizon AI supercomputer (Building A) | Cirrascale Cloud Services, LLC (registered occupant, 'SDC - Austin Tandem Data Center') | JS Data Center LLC (registered occupant, SDC Austin III/IV)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Sabey Data Centers SDC Austin Campus (Round Rock): power and grid

operational

Key data: Utility region: ERCOT | Grid area: ERCOT South Central / Austin-Central Texas load zone | Gross MW: 84 | Grid/market records: Texas Comptroller Qualifying Data Center registration 'SDC - Austin Tandem Data Center', effective 03/13/2024; owner SDC - Austin LLC; occupant Cirrascale Cloud Services, LLC; operator SDC - Austin LLC | Texas Comptroller Qualifying LARGE Data Center Project registration 'SDC Austin III LLC dba SDC Austin IV LLC', effective 08/24/2026; owner SDC Austin III LLC; occupant JS Data Center LLC; operator Sabey Data Center Properties LLC

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Sabey Data Centers SDC Austin Campus (Round Rock): water and cooling

operational

Key data: Water utility: City of Round Rock Water | Water source: City of Round Rock Water (Colorado River / LCRA basin) | Water demand: ~2,000,000 gallons/year (~5,500 gal/day) for Building A per City of Round Rock monitoring data | Cooling: Liquid cooling (primary; ~86% of deployments per Sabey) plus air cooling

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Sabey Data Centers SDC Austin Campus (Round Rock): permits and jurisdiction

operational

Key data: Permit IDs: Comptroller Qualifying Data Center registration (SDC - Austin Tandem Data Center),Comptroller Qualifying Large Data Center Project registration (SDC Austin III LLC dba SDC Austin IV LLC) | Comptroller Qualifying Data Center registration (SDC - Austin Tandem Data Center) | Comptroller Qualifying Large Data Center Project registration (SDC Austin III LLC dba SDC Austin IV LLC) | Jurisdictions: City of Round Rock | Williamson County | City of Round Rock Water | Texas Comptroller | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Sabey Data Centers SDC Austin Campus (Round Rock): civic and community

operational

City of Round Rock publishes data center monitoring information, including verified water use for Building A

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Sabey Data Centers SDC Austin Campus (Round Rock): environment and site

operational

Liquid cooling keeps measured water use to roughly 5,500 gal/day, far below evaporative benchmarks for comparable load

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

operational

Key data: Surrounding infrastructure: Adaptive reuse of the former Sears call center site on Louis Henna Blvd

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Sabey Data Centers SDC Austin Campus (Round Rock): timeline

operational

Comptroller Qualifying Data Center registration effective (Cirrascale as occupant)

Claim classification: Not yet assigned

Status date: 2024-03-13

Open source 1 →

operational

Building A (213,000 sq ft, ~30 MW) completed; selected by TACC for the Horizon AI supercomputer

Claim classification: Not yet assigned

Status date: 2024-10-01

Open source 1 →

operational

Building B (54 MW, liquid-cooling-ready) breaks ground

Claim classification: Not yet assigned

Status date: 2025-07-01

Open source 1 →

operational

Comptroller Qualifying Large Data Center Project registration effective for SDC Austin III/IV

Claim classification: Not yet assigned

Status date: 2026-08-24

Open source 1 →

operational

First capacity in Building B available

Claim classification: Not yet assigned

Status date: 2027-07-01

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Sabey Data Centers SDC Austin Campus (Round Rock) Data Center Project | Round Rock | Compute Equity Atlas