operational
TDLR Architectural Barriers project TABS2024002539 registered on October 5, 2023 for '06-23 Smith County IT Data Center Improvements' at the Smith County Annex.
Key data: TABS2024002539; registered 2023-10-05
Claim classification: official_record · Verification: primary_record · Retrieved: 2026-09-05
Status date: 2024-12-20
Open source 1 →
operational
TDLR project TABS2024002539, '06-23 Smith County IT Data Center Improvements', covers renovating existing office space into a larger data center plus generator, pad and enclosure replacement at 200 E. Ferguson St., Suite 213, Tyler; 1,500 sq ft, $2,000,000, registered October 5, 2023, work November 1, 2023 to December 20, 2024.
Key data: TABS2024002539; 1,500 sq ft; $2,000,000
Claim classification: official_record · Verification: primary_source · Retrieved: 2026-09-05
Status date: 2024-12-20
Limitation: Public-funds project; completion not separately confirmed.
Open source 1 →