Soluna Project Kati

This record consolidates 17 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
17linked evidence rows
Project facts

Location and operating record

Operator / developerSoluna Holdings, Inc. (NASDAQ: SLNH)
JurisdictionNOT_FOUND (unincorporated Willacy County), TX
AddressNOT_FOUND
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity166 MW
AliasesSoluna Project Kati · Project Kati (Kati 1 and Kati 2) · Kati · Soluna Kati
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure1 rows
SOURCE RECORD

Soluna Project Kati: source record

under_construction

Kati 1 = 83 MW (48 MW Galaxy anchor + 35 MW Soluna Bitcoin hosting); Kati 2 = 83 MW planned for AI/HPC. Represents a crypto-to-AI convertible campus in the Rio Grande Valley.

Key data: NOT_FOUND | ERCOT (South Texas wind zone) | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Soluna Project Kati: ownership and profile

under_construction

Developer: Soluna Computing | Owner: Soluna Holdings, Inc. | County: Willacy | Research region: East Texas / South Texas-RGV / Statewide Rural Gap Pass | Tenants/customers: Galaxy Digital (48 MW anchor customer, Kati 1) | Soluna proprietary Bitcoin hosting (35 MW, Kati 1)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Soluna Project Kati: power and grid

under_construction

Key data: Grid area: ERCOT (South Texas wind zone) | Gross MW: 166 | IT load MW: 166

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Soluna Project Kati: water and cooling

under_construction

Key data: Water demand: Zero-water cooling stated | Cooling: air/immersion-style zero-water cooling (no water consumption stated)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Soluna Project Kati: permits and jurisdiction

under_construction

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

CIVIC AND COMMUNITY

Soluna Project Kati: civic and community

under_construction

Uses curtailed wind energy; local jobs and landowner payments cited by developer

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Soluna Project Kati: environment and site

under_construction

Zero-water cooling

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Consumes otherwise-curtailed wind generation

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Co-located with wind generation

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Partners: EDF power solutions, Masdar, Spring Lane Capital, Generate Capital

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Soluna Project Kati: timeline

under_construction

Groundbreaking

Claim classification: Not yet assigned

Status date: 2025-09-18

Open source 1 →

under_construction

Phase 1 (Kati 1) targeted online

Claim classification: Not yet assigned

Status date: 2026 (early)

Open source 1 →

CAPACITY GROSS POWER

Soluna Project Kati: capacity gross power

under_construction

Project Kati is a 166 MW campus in two 83 MW phases: Kati 1 with 48 MW anchored by Galaxy plus 35 MW of Soluna Bitcoin hosting, and Kati 2 with 83 MW for AI/HPC.

Key data: 166 MW total (83 MW + 83 MW)

Claim classification: operator_claim · Verification: single_source · Retrieved: 2026-09-05

Status date: 2025-09-18

Limitation: No ERCOT interconnection record retrieved.

Open source 1 →

PROJECT TIMELINE

Soluna Project Kati: project timeline

under_construction

Soluna broke ground on September 18, 2025 and expected phase 1 online in early 2026.

Key data: Groundbreaking 2025-09-18; phase 1 early 2026

Claim classification: operator_claim · Verification: single_source · Retrieved: 2026-09-05

Status date: 2025-09-18

Limitation: Energization not independently confirmed.

Open source 1 →

POWER SUPPLIER

Soluna Project Kati: power supplier

under_construction

The site is powered by curtailed wind generation, with EDF power solutions, Masdar, Spring Lane Capital and Generate Capital named as partners.

Key data: Wind-powered; EDF/Masdar partners

Claim classification: operator_claim · Verification: single_source · Retrieved: 2026-09-05

Limitation: PPA terms not disclosed.

Open source 1 →

WATER DEMAND

Soluna Project Kati: water demand

under_construction

Soluna states the facility uses zero water for cooling.

Key data: Zero-water cooling

Claim classification: operator_claim · Verification: single_source · Retrieved: 2026-09-05

Limitation: No permit corroboration.

Open source 1 →

JOBS

Soluna Project Kati: jobs

under_construction

Soluna cites roughly 75 construction jobs and 18 or more permanent positions.

Key data: ~75 construction; 18+ permanent

Claim classification: operator_claim · Verification: single_source · Retrieved: 2026-09-05

Limitation: No county agreement retrieved.

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Soluna Project Kati Data Center Project | NOT_FOUND (unincorporated Willacy County) | Compute Equity Atlas