Compute Equity Atlas
← National map
Source-backed project record · TX

Stargate Milam County Data Center (Freebird)

This record consolidates 15 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
15linked evidence rows
Project facts

Location and operating record

Operator / developerSB Energy (SoftBank Group subsidiary)
JurisdictionNear Burlington, TX
AddressNOT_FOUND
Location precisionlocality centroid
CoordinatesNot published; no coordinate inferred
Capacity1200 MW
AliasesStargate Milam County Data Center (Freebird) · Freebird campus near Burlington · Freebird Data Center Phase 1 / DC01 · Milam County Data Center · Stargate Milam
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Stargate Milam County Data Center (Freebird): source record

under_construction

Rural gap find in Milam County. Phase 1 single-story 548,950 sq ft with four data halls; facility overall described as 1.2 GW with OpenAI as tenant and SB Energy as operator.

Key data: NOT_FOUND | ERCOT | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Stargate Milam County Data Center (Freebird): ownership and profile

under_construction

Developer: SB Energy | Owner: Comptroller registrations list MDC Building 1, LLC; Orion DC I, LLC; Milam County DC, LLC; and MDC Building 2, LLC | Property entity: MDC Building 1, LLC / MDC Building 2, LLC | Permit applicant: SB Energy (TDLR filing) | County: Milam | Research region: East Texas / South Texas-RGV / Statewide Rural Gap Pass | Tenants/customers: OpenAI (1.2 GW data center lease for the initial buildout)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Stargate Milam County Data Center (Freebird): power and grid

under_construction

Key data: Grid area: ERCOT | Gross MW: 1200 | Requested load MW: 1200

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Stargate Milam County Data Center (Freebird): water and cooling

under_construction

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Stargate Milam County Data Center (Freebird): permits and jurisdiction

under_construction

Key data: Jurisdictions: Milam County | Texas Department of Licensing and Regulation | Texas Comptroller | ERCOT | Tax incentives: [object Object],[object Object] | {"agreement_name":"Texas Comptroller qualifying large data center registration - Milam County Data Center","agreement_number":"NOT_FOUND","approval_date":"2025-12-09 (effective date)","estimated_value":"NOT_FOUND","government_entity":"Texas Comptroller of Public Accounts","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php","term":"NOT_FOUND"} | {"agreement_name":"Texas Comptroller qualifying large data center registration - Milam County Data Center Phase 2 (MDC Building 2, LLC)","agreement_number":"NOT_FOUND","approval_date":"2026-06-10 (effective date)","estimated_value":"NOT_FOUND","government_entity":"Texas Comptroller of Public Accounts","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php","term":"NOT_FOUND"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Stargate Milam County Data Center (Freebird): environment and site

under_construction

Key data: Surrounding infrastructure: Design firm Corgan Architects

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: OpenAI and SoftBank each investing $500 million in SB Energy

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Stargate Milam County Data Center (Freebird): timeline

under_construction

Comptroller data center exemption effective for Milam County Data Center (MDC Building 1, LLC / Orion DC I, LLC / Milam County DC, LLC)

Claim classification: Not yet assigned

Status date: 2025-12-09

Open source 1 →

under_construction

Phase one of Freebird officially topped out

Claim classification: Not yet assigned

Status date: 2026-03

Open source 1 →

under_construction

Comptroller data center exemption effective for Phase 2 (MDC Building 2, LLC)

Claim classification: Not yet assigned

Status date: 2026-06-10

Open source 1 →

under_construction

TDLR filing detail reported: 548,950 sq ft single-story building with four data halls, ~$470M, completion 15 October

Claim classification: Not yet assigned

Status date: 2026-07-14

Open source 1 →

BUILDING SQFT

Stargate Milam County Data Center (Freebird): building sqft

under_construction

A TDLR filing shows the first phase as a single-story 548,950 sq ft building with four data halls, estimated at $470 million, designed by Corgan Architects.

Key data: 548,950 sq ft; four data halls; $470M

Claim classification: reported_fact · Verification: single_source · Retrieved: 2026-09-05

Status date: 2026-07-14

Limitation: TDLR project number not stated in the article.

Open source 1 →

TENANT CUSTOMER

Stargate Milam County Data Center (Freebird): tenant customer

under_construction

OpenAI is identified as the tenant and SB Energy, a SoftBank subsidiary, as the developer and operator of the 1.2 GW facility.

Key data: Tenant OpenAI; developer/operator SB Energy

Claim classification: reported_fact · Verification: single_source · Retrieved: 2026-09-05

Status date: 2026-07-14

Limitation: Lease terms not disclosed.

Open source 1 →

PROJECT TIMELINE

Stargate Milam County Data Center (Freebird): project timeline

under_construction

Phase one topped out in March 2026 and a completion date of 15 October is listed in the filing.

Key data: Topped out March 2026; completion 15 October

Claim classification: reported_fact · Verification: single_source · Retrieved: 2026-09-05

Status date: 2026-03

Limitation: The completion year is not stated in the source.

Open source 1 →

TAX INCENTIVES

Stargate Milam County Data Center (Freebird): tax incentives

under_construction

The Texas Comptroller's qualifying large data center list registers 'Milam County Data Center' effective December 9, 2025 with MDC Building 1, LLC, Orion DC I, LLC and Milam County DC, LLC, and a Phase 2 registration effective June 10, 2026 under MDC Building 2, LLC.

Key data: Comptroller registrations eff. 2025-12-09 and 2026-06-10

Claim classification: official_record · Verification: primary_source · Retrieved: 2026-09-05

Status date: 2026-06-10

Limitation: The state list does not link these entities to SB Energy or OpenAI.

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Stargate Milam County Data Center (Freebird) Data Center Project | Near Burlington | Compute Equity Atlas