Stargate Milam County Data Center (Freebird)

This record consolidates 3 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
VERIFIED_PRIMARYbest evidence tier
3linked evidence rows
Project facts

Location and operating record

Operator / developerSB Energy (SoftBank Group subsidiary)
JurisdictionNear Burlington, TX
AddressNOT_FOUND
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity1200 MW
AliasesStargate Milam County Data Center (Freebird) · Freebird campus near Burlington
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Stargate Milam County Data Center (Freebird): source record

under_construction

Rural gap find in Milam County. Phase 1 single-story 548,950 sq ft with four data halls; facility overall described as 1.2 GW with OpenAI as tenant and SB Energy as operator.

Key data: NOT_FOUND | ERCOT | NOT_FOUND | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05