Texas Critical Data Centers (TCDC) Ector County Campus

This record consolidates 22 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
CORROBORATEDbest evidence tier
22linked evidence rows
Project facts

Location and operating record

Operator / developerTexas Critical Data Centers LLC (50/50 JV of New Era Helium and Sharon AI)
JurisdictionOdessa, TX
AddressNot published
Location precisionlocality centroid
Coordinates31.880461, -102.345314
Capacity250 MW
AliasesTexas Critical Data Centers (TCDC) Ector County Campus · TCDC AI Data Center Campus · TCDC · New Era Helium / Sharon AI JV campus
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Texas Critical Data Centers (TCDC) Ector County Campus: source record

under_construction

Originally scoped at 90 MW in late 2024, now 250 MW with potential beyond 1 GW. New Era Helium supplies gas under a five-year fixed-cost agreement with extension options. Parent company renamed New Era Energy & Digital (Nasdaq: NUAI).

Key data: Behind-the-meter natural gas generation; MOU with PowerForward Energy for 250 MW on-site | ERCOT | City of Odessa (via Industrial District application)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Texas Critical Data Centers (TCDC) Ector County Campus: ownership and profile

under_construction

Developer: Texas Critical Data Centers LLC | Owner: Texas Critical Data Centers LLC; land acquired from Grow Odessa | Permit applicant: Applicant for an Industrial District agreement with the City of Odessa (water/wastewater service) | County: Ector | Research region: Abilene-West Central Texas / Midland-Odessa-Permian Basin | Tenants/customers: Negotiating an NNN powered-shell lease with an unnamed leading hyperscaler (as of December 2025)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Texas Critical Data Centers (TCDC) Ector County Campus: power and grid

under_construction

Key data: Utility: Behind-the-meter natural gas generation; MOU with PowerForward Energy for 250 MW on-site | Utility region: ERCOT West | Grid area: ERCOT | Gross MW: 250 | Requested load MW: 250 | Onsite generation MW: 250

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Texas Critical Data Centers (TCDC) Ector County Campus: water and cooling

under_construction

Key data: Water utility: City of Odessa (via Industrial District application)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Texas Critical Data Centers (TCDC) Ector County Campus: permits and jurisdiction

under_construction

Key data: Jurisdictions: Ector County | City of Odessa (Industrial District) | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Texas Critical Data Centers (TCDC) Ector County Campus: environment and site

under_construction

Reciprocating natural gas engines for power

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Planned carbon capture, utilization and storage sequestering roughly 250,000 metric tons of CO2 per year

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Project may qualify for 45Q tax credits

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Proximity to natural gas resources

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: Fiber optic networks

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

under_construction

Key data: Surrounding infrastructure: CO2 pipeline infrastructure

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Texas Critical Data Centers (TCDC) Ector County Campus: timeline

under_construction

New Era Helium / Sharon AI joint venture finalized

Claim classification: Not yet assigned

Status date: 2025-01

Open source 1 →

under_construction

Letter of intent signed on the Ector County site

Claim classification: Not yet assigned

Status date: 2025-02-28

Open source 1 →

under_construction

TCDC closes 235-acre land acquisition from Grow Odessa; LOI for an additional 203 acres

Claim classification: Not yet assigned

Status date: NOT_FOUND (reported by DCD)

Open source 1 →

under_construction

New Era Energy & Digital (Nasdaq: NUAI) reports 438 acres assembled, site clearing and earthwork underway, soil sampling, and NNN powered-shell lease negotiations with a leading hyperscaler

Claim classification: Not yet assigned

Status date: 2025-12-11

Open source 1 →

under_construction

Phase 1 target of 100 MW online

Claim classification: Not yet assigned

Status date: 2026-12 (target)

Open source 1 →

under_construction

Remaining capacity targeted operational

Claim classification: Not yet assigned

Status date: 2027 mid (target)

Open source 1 →

CAMPUS ACRES

Texas Critical Data Centers (TCDC) Ector County Campus: campus acres

under_construction

TCDC, a 50/50 joint venture of New Era Helium and Sharon AI, closed on 235 acres purchased from Grow Odessa and holds a letter of intent for an additional 203 acres for 438 acres total.

Key data: 235 acres closed; LOI for 203 more; 438 acres total

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Open source 1 →

CAPACITY GROSS POWER

Texas Critical Data Centers (TCDC) Ector County Campus: capacity gross power

under_construction

The project was originally scoped at 90 MW in late 2024 and now targets 250 MW with potential beyond 1 GW, powered by reciprocating natural gas engines under an MOU with PowerForward Energy for 250 MW of on-site generation.

Key data: 250 MW target; >1 GW potential; 250 MW on-site gas via PowerForward MOU

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Open source 1 →

WATER SUPPLIER

Texas Critical Data Centers (TCDC) Ector County Campus: water supplier

under_construction

TCDC filed an Industrial District application with the City of Odessa to obtain water and wastewater service, and the site was selected for proximity to natural gas, fiber optic networks and CO2 pipeline infrastructure.

Key data: Industrial District application with City of Odessa for water/wastewater

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Open source 1 →

PROJECT TIMELINE

Texas Critical Data Centers (TCDC) Ector County Campus: project timeline

under_construction

New Era Energy & Digital (Nasdaq: NUAI) reported 438 acres assembled with site clearing, earthwork and soil sampling underway and negotiations on a triple-net powered-shell lease with an unnamed leading hyperscaler.

Key data: 438 acres; earthwork underway; NNN powered-shell lease in negotiation

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2025-12-11

Open source 1 →

ENVIRONMENTAL IMPACT

Texas Critical Data Centers (TCDC) Ector County Campus: environmental impact

under_construction

New Era Helium will supply natural gas under a five-year fixed-cost agreement and implement carbon capture, utilization and storage sequestering roughly 250,000 metric tons of CO2 per year, potentially qualifying for 45Q credits; phase 1 targets 100 MW by December 2026 with the remainder by mid-2027.

Key data: ~250,000 metric tons CO2/yr sequestration; phase 1 100 MW by Dec 2026

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Texas Critical Data Centers (TCDC) Ector County Campus Data Center Project | Odessa | Compute Equity Atlas