Source-backed project record · TX

Tract Medina Technology Park

This record consolidates 11 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
SOURCE_BACKEDbest evidence tier
11linked evidence rows
Project facts

Location and operating record

Operator / developerNOT_FOUND (land developer delivering powered shell sites to future operators)
JurisdictionMedina County (unincorporated), TX
AddressNOT_FOUND
Location precisionlocality centroid
CoordinatesNot published; no coordinate inferred
CapacityNot established
AliasesTract Medina Technology Park · Medina Technology Park
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Tract Medina Technology Park: source record

planned

Tract is a land-and-power aggregator: the park is designed to be sold or leased to data center operators, so no end operator or tenant is identified. Confirms Medina Electric Cooperative rather than CPS Energy as the serving utility for this part of the region.

Key data: Medina Electric Cooperative | ERCOT | East Medina County Special Utility District | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Tract Medina Technology Park: ownership and profile

planned

Developer: Tract | Owner: Tract | County: Medina | Research region: San Antonio

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Tract Medina Technology Park: power and grid

planned

Key data: Utility: Medina Electric Cooperative | Utility region: Medina Electric Cooperative service territory (not CPS Energy) | Grid area: ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Tract Medina Technology Park: water and cooling

planned

Key data: Water utility: East Medina County Special Utility District

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Tract Medina Technology Park: permits and jurisdiction

planned

Key data: Jurisdictions: Medina County | State of Texas | ERCOT | Medina Electric Cooperative | East Medina County SUD

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Tract Medina Technology Park: timeline

planned

Tract announces Medina Technology Park, a 265-acre master-planned data center park with 500 MW of planned capacity and energization targeted for mid-2028

Claim classification: Not yet assigned

Open source 1 →

CAPACITY GROSS POWER

Tract Medina Technology Park: capacity gross power

planned

Developer project page states the planned campus capacity.

Key data: 500 MW planned

Claim classification: developer_self_disclosure · Verification: partially_verified · Retrieved: 2026-09-05

Limitation: Not corroborated by a utility or ERCOT filing retrieved this session.

Open source 1 →

CAMPUS ACRES

Tract Medina Technology Park: campus acres

planned

Developer project page states the land area.

Key data: 265 acres

Claim classification: developer_self_disclosure · Verification: partially_verified · Retrieved: 2026-09-05

Open source 1 →

POWER SUPPLIER

Tract Medina Technology Park: power supplier

planned

Developer identifies the serving electric utility, which is a cooperative rather than the San Antonio municipal utility.

Key data: Medina Electric Cooperative

Claim classification: developer_self_disclosure · Verification: partially_verified · Retrieved: 2026-09-05

Limitation: Interconnection agreement not located.

Open source 1 →

WATER SUPPLIER

Tract Medina Technology Park: water supplier

planned

Developer identifies the water provider for the park.

Key data: East Medina County Special Utility District

Claim classification: developer_self_disclosure · Verification: partially_verified · Retrieved: 2026-09-05

Limitation: Water demand volume not disclosed.

Open source 1 →

PROJECT TIMELINE

Tract Medina Technology Park: project timeline

planned

Developer states the targeted energization date.

Key data: Energization targeted mid-2028

Claim classification: developer_self_disclosure · Verification: partially_verified · Retrieved: 2026-09-05

Limitation: Target date, not a committed milestone.

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Tract Medina Technology Park Data Center Project | Medina County (unincorporated) | Compute Equity Atlas