Vantage Data Centers Frontier Campus

This record consolidates 16 research observations while retaining source distinctions, location precision and unresolved fields.

under_constructionproject status
CORROBORATEDbest evidence tier
16linked evidence rows
Project facts

Location and operating record

Operator / developerVantage Data Centers Management Company, LLC
JurisdictionAbilene (mailing address), TX
Address246 PR 1604, Bldg 3, Abilene, TX (TDLR filing for TX303); 200 block of PR 1604
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity1400 MW
AliasesVantage Data Centers Frontier Campus · Frontier · Project Frontier · Vantage TX301-TX310 · Vantage DC Abilene TX3
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Vantage Data Centers Frontier Campus: source record

under_construction

COUNTY CONFLICT RESOLVED TOWARD SHACKELFORD: TDLR TABS registration lists Shackelford County and DCD reporting confirms Shackelford County, ~35 miles NE of Abilene, despite an Abilene 79601 mailing address and aggregator listings placing it in Taylor County. Included here because it is functionally part of the Abilene cluster; Shackelford is adjacent to, not inside, the brief's listed county set. Reported building/cost figures differ across sources ($11B local reporting vs >$25B DCD).

Key data: NOT_FOUND | ERCOT

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Vantage Data Centers Frontier Campus: ownership and profile

under_construction

Developer: Vantage Data Centers | Owner: Vantage Data Centers TX301-TX310, LLC | Property entity: Vantage Data Centers TX303, LLC (and TX301, TX302, TX304-TX310, LLC) | Permit applicant: Vantage Data Centers TX303, LLC (TDLR project registration) | County: Shackelford | Research region: Abilene-West Central Texas / Midland-Odessa-Permian Basin | Tenants/customers: Oracle America Cloud Services, LLC (registered occupant) | OpenAI (Stargate)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Vantage Data Centers Frontier Campus: power and grid

under_construction

Key data: Utility region: ERCOT West | Grid area: ERCOT | Gross MW: 1400

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Vantage Data Centers Frontier Campus: water and cooling

under_construction

Key data: Cooling: Air-cooled and liquid-cooled; >250 kW per rack

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Vantage Data Centers Frontier Campus: permits and jurisdiction

under_construction

Key data: Permit IDs: TDLR TABS2026024088 (TX303 / Project Frontier, Bldg 3) | Jurisdictions: Shackelford County | Texas Department of Licensing and Regulation | Texas Comptroller of Public Accounts | ERCOT | Tax incentives: [object Object] | {"agreement_name":"Texas Comptroller Qualifying Large Data Center Project registrations - TX 301 through TX 310 Data Center","agreement_number":"LD467875, LD960266, LD394780, LD753524, LD677523, LD881935, LD696769, LD772770, LD884265, LD781786","approval_date":"2025-10-08","estimated_value":"State sales-and-use tax exemption","government_entity":"Texas Comptroller of Public Accounts","investment_commitment":"NOT_FOUND","jobs_commitment":"NOT_FOUND","source_url":"https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php","term":"NOT_FOUND"}

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

ENVIRONMENT AND SITE

Vantage Data Centers Frontier Campus: environment and site

under_construction

Key data: Surrounding infrastructure: Three meet-me rooms per building

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Vantage Data Centers Frontier Campus: timeline

under_construction

Vantage registers TX 301 - TX 310 Data Centers with the Texas Comptroller (occupant Oracle America Cloud Services)

Claim classification: Not yet assigned

Status date: 2025-10-08

Open source 1 →

under_construction

TDLR construction registration for TX303 / Project Frontier Bldg 3: start 2025-10-30, completion 2027-04-19, $990M, 344,796 sq ft

Claim classification: Not yet assigned

Status date: 2026-06-29

Open source 1 →

under_construction

Local reporting: 10 buildings, ~$11B, opening 2027-2028, 200 block of PR 1604

Claim classification: Not yet assigned

Status date: 2026-07-02

Open source 1 →

under_construction

Vantage hosts groundbreaking ceremony for Frontier campus; 1.4 GW, 1,200 acres, 10 buildings, >$25B, first building operational H2 2026

Claim classification: Not yet assigned

Status date: NOT_FOUND (report published after October 2025 Stargate announcements)

Open source 1 →

EXACT LOCATION

Vantage Data Centers Frontier Campus: exact location

under_construction

The TDLR construction registration for Project Frontier building TX303 lists the site at 246 PR 1604, Bldg 3, Abilene TX 79601 and records the county as Shackelford, not Taylor.

Key data: 246 PR 1604, Abilene TX 79601; County: Shackelford

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2026-06-29

Limitation: Abilene mailing address sits in a different county than the recorded project county; aggregators commonly list this campus in Taylor County.

Open source 1 →

PROJECT COST

Vantage Data Centers Frontier Campus: project cost

under_construction

The TDLR filing records a $990,000,000 construction cost and 344,796 sq ft for building TX303 alone, with construction starting 2025-10-30 and completion scheduled 2027-04-19.

Key data: $990,000,000; 344,796 sq ft; completion 2027-04-19

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2026-06-29

Open source 1 →

under_construction

Local reporting describes the campus as ten buildings worth nearly $11 billion opening in 2027, located in the 200 block of PR 1604, with county filings placing it in Shackelford County.

Key data: 10 buildings; ~$11 billion; opening 2027-2028

Claim classification: CONFLICTING · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2026-07-02

Limitation: Conflicts with the >$25B figure reported by DatacenterDynamics.

Open source 1 →

OWNERSHIP CHAIN

Vantage Data Centers Frontier Campus: ownership chain

under_construction

The TDLR filing names Vantage Data Centers TX303, LLC of 2820 Northwestern Pkwy, Santa Clara CA as owner, with Kiewit as design firm.

Key data: Owner: Vantage Data Centers TX303, LLC; design firm Kiewit

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2026-06-29

Open source 1 →

CAPACITY GROSS POWER

Vantage Data Centers Frontier Campus: capacity gross power

under_construction

DatacenterDynamics reports the Frontier campus at 1.4 GW across ten single-story buildings on 1,200 acres totalling roughly 3.7 million sq ft, with more than $25 billion of planned investment and the first building operational in the second half of 2026.

Key data: 1.4 GW; 1,200 acres; 10 buildings; ~3.7M sq ft; >$25B

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Open source 1 →

TENANT CUSTOMER

Vantage Data Centers Frontier Campus: tenant customer

under_construction

The campus is tied to Oracle and OpenAI's Stargate expansion, and the Comptroller registry lists Oracle America Cloud Services, LLC as occupant of TX 301 through TX 310 Data Center.

Key data: Occupant: Oracle America Cloud Services, LLC; hosting hardware for OpenAI

Claim classification: SOURCED_FACT · Verification: VERIFIED · Retrieved: 2026-09-05

Status date: 2025-10-08

Open source 1 →

Sources

Evidence and provenance

Open TX state research →

Vantage Data Centers Frontier Campus Data Center Project | Abilene (mailing address) | Compute Equity Atlas