Westland Bunker

This record consolidates 14 research observations while retaining source distinctions, location precision and unresolved fields.

operationalproject status
CORROBORATEDbest evidence tier
14linked evidence rows
Project facts

Location and operating record

Operator / developerWestland Bunker
JurisdictionMontgomery, TX
Address550 Club Drive
Location precisionstreet address
CoordinatesNot published; no coordinate inferred
Capacity12 MW
AliasesWestland Bunker · Westland Bunker / Club Drive campus · Westland Bunker Data Center · Louis Kung nuclear bunker
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure0 rows
SOURCE RECORD

Westland Bunker: source record

operational

CONFLICT: campus acreage reported as both 52 and 58 acres. Composition: 140,000 sq ft underground hardened facility plus a 105,000 sq ft above-ground building, aggregated as ~240,000 sq ft.

Key data: Entergy Texas (Montgomery County) | ERCOT | NOT_FOUND

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

OWNERSHIP AND PROFILE

Westland Bunker: ownership and profile

operational

Developer: Curtis Development LLC (2001 conversion) | Owner: Montgomery LP / Pudge Properties | Property entity: Montgomery LP | County: Montgomery | Research region: Houston / Gulf Coast

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

POWER AND GRID

Westland Bunker: power and grid

operational

Key data: Utility: Entergy Texas (Montgomery County) | Utility region: ERCOT Houston (Coast) load zone | Grid area: ERCOT | Gross MW: 12

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

WATER AND COOLING

Westland Bunker: water and cooling

operational

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

PERMITS AND JURISDICTION

Westland Bunker: permits and jurisdiction

operational

Key data: Permit IDs: TDLR TABS2025017148 | Jurisdictions: Montgomery County | City of Montgomery | Texas Department of Licensing and Regulation (TABS)

Claim classification: Not yet assigned

Status date: 2026-09-05

Open source 1 →

TIMELINE

Westland Bunker: timeline

operational

Underground structure built as a nuclear shelter

Claim classification: Not yet assigned

Status date: 1981

Open source 1 →

operational

Converted to a data center

Claim classification: Not yet assigned

Status date: 2004

Open source 1 →

operational

Underground data center upgraded

Claim classification: Not yet assigned

Status date: 2008

Open source 1 →

operational

Second, above-ground 105,000 sq ft data center with 5 halls / 12MW added

Claim classification: Not yet assigned

Status date: 2014

Open source 1 →

operational

TDLR project TABS2025017148 registered

Claim classification: Not yet assigned

Status date: 2025-04-21

Open source 1 →

operational

Campus listed for sale at $39M, reported 77% leased

Claim classification: Not yet assigned

Status date: 2025

Open source 1 →

PROJECT STATUS

Westland Bunker: project status

operational

The Westland Bunker campus at 550 Club Drive, Montgomery - a 1981 nuclear shelter converted to a data center in 2004 and expanded in 2008 and 2014 - was listed for sale at $39 million while 77% leased.

Key data: $39,000,000 asking price; 77% leased

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2025

Open source 1 →

CAPACITY GROSS POWER

Westland Bunker: capacity gross power

operational

The campus combines a 140,000 sq ft underground hardened data center with a 105,000 sq ft above-ground building added in 2014 containing five data halls and 12MW.

Key data: 12MW; 140,000 sq ft underground + 105,000 sq ft above ground

Claim classification: REPORTED_FACT · Verification: SINGLE_SOURCE · Retrieved: 2026-09-05

Status date: 2014

Limitation: CONFLICT: campus acreage is reported as both 52 and 58 acres across sources.

Open source 1 →

OTHER PERMITS

Westland Bunker: other permits

operational

TDLR project TABS2025017148 was registered on 4/21/2025 for the Westland Bunker site.

Key data: TDLR TABS2025017148, registered 2025-04-21

Claim classification: OFFICIAL_RECORD · Verification: PRIMARY_SOURCE · Retrieved: 2026-09-05

Status date: 2025-04-21

Open source 1 →