Source-backed project record · MO

White Cloud Acres

This record consolidates 19 research observations while retaining source distinctions, location precision and unresolved fields.

proposed_or_reviewproject status
CORROBORATEDbest evidence tier
19linked evidence rows
Project facts

Location and operating record

Operator / developerReLoad (Chicago), acquired by Scale Microgrids (New Jersey) in February 2026
JurisdictionMaryville (southern Nodaway County), MO
AddressNot published
Location precisionlocality centroid
Coordinates40.342515, -94.870048
CapacityNot established
AliasesWhite Cloud Acres · White Cloud Acres AI Data Center
Evidence coverage

What has been researched

Project profile0 rows
Intent / permits0 rows
Civic / infrastructure3 rows
SOURCE RECORD

White Cloud Acres: source record

planned

600 MW data center with a co-located natural gas energy facility. Investment figures: more than $6 billion / $6.3 billion combined, of which about $4 billion is attributed to the data center by missouridatacenters.org. The 600 MW is described as data center demand; the gas facility capacity is not separately stated, so onsite_generation_mw is left null. Electric utility not documented; Evergy Missouri West operates the nearby Mullin Creek substation and is building a separate 440 MW gas plant five miles south of Maryville, but no source links that plant to this project.

Key data: Not verified in fetched sources

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

OWNERSHIP AND PROFILE

White Cloud Acres: ownership and profile

planned

Developer: ReLoad (Chicago), acquired by Scale Microgrids (New Jersey) in February 2026 | Owner: White Cloud Acres LLC | County: Nodaway | Research region: Northwest Missouri

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

POWER AND GRID

White Cloud Acres: power and grid

planned

Key data: Grid area: Not verified in fetched sources | Requested load MW: 600

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

planned

The White Cloud Acres information center describes a 600 MW data center paired with a natural gas energy facility in southern Nodaway County near Maryville, with multiple buildings of more than one million sq ft each, closed-loop cooling, a feasibility study on reclaimed wastewater for gas plant emissions controls and a decision expected by the end of June 2026.

Key data: 600 MW data center plus on-site natural gas facility

Claim classification: proposal_or_announced_commitment · Verification: verified_by_primary_source · Retrieved: 2026-09-13

Status date: 2026-06

Limitation: Developer self-report; no county approval, utility agreement or interconnection filing verified.

Open source 1

WATER AND COOLING

White Cloud Acres: water and cooling

planned

Key data: Water source: Feasibility study underway on using reclaimed wastewater for gas plant emissions controls | Cooling: Closed-loop cooling

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

PERMITS AND JURISDICTION

White Cloud Acres: permits and jurisdiction

planned

Key data: Jurisdictions: Nodaway County | Missouri

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

CORROBORATED

Nodaway County commissioners scheduled a meeting with Scale Microgrids about the proposed data center on 2026-06-03, the project's first significant public airing.

Key data: County commission meeting with Scale Microgrids 2026-06-03

Claim classification: documented_fact · Verification: source_backed_unverified · Retrieved: 2026-09-13

Limitation: No approval decision reported in this item.

Open source 1

VERIFIED_PRIMARY

Nodaway County Commission minutes for 2026 document commission proceedings related to the proposed data center and the county's due-diligence posture.

Key data: County commission minutes reference the proposal

Claim classification: documented_fact · Verification: verified_by_primary_source · Retrieved: 2026-09-13

Limitation: Minutes PDF is a compiled year-to-date document; specific motions were not individually transcribed here.

Open source 1

CIVIC AND COMMUNITY

White Cloud Acres: civic and community

planned

Developer states it has no NDAs with governing bodies

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

planned

First public presentation to the Nodaway County Commission in June 2026

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

planned

Nodaway County Commission was set to enact a proposed six-month due-diligence data center moratorium on 2026-07-21

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

ENVIRONMENT AND SITE

White Cloud Acres: environment and site

planned

Key data: Surrounding infrastructure: Co-located natural gas energy facility planned on the same site

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

planned

Key data: Surrounding infrastructure: Multiple buildings of more than 1 million sq ft each

Claim classification: Not yet assigned

Status date: 2026-09-13

Open source 1

TIMELINE

White Cloud Acres: timeline

planned

Project proposed

Claim classification: Not yet assigned

Status date: 2025-12

Open source 1

planned

ReLoad acquired by Scale Microgrids

Claim classification: Not yet assigned

Status date: 2026-02

Open source 1

planned

Nodaway County commissioners scheduled a meeting with Scale Microgrids about the proposed data center

Claim classification: Not yet assigned

Status date: 2026-06-03

Open source 1

planned

Decision expected by the end of June 2026

Claim classification: Not yet assigned

Status date: 2026-06

Open source 1

planned

Nodaway County Commission set to enact a proposed six-month data center moratorium

Claim classification: Not yet assigned

Status date: 2026-07-21

Open source 1

ECONOMIC AND TAX

White Cloud Acres: economic and tax

SOURCE_BACKED

MissouriDataCenters.org reports the White Cloud Acres project as a more than $6 billion / $6.3 billion total investment of which about $4 billion is attributed to the data center, proposed in December 2025 by ReLoad of Chicago, which was acquired by New Jersey-based Scale Microgrids in February 2026.

Key data: >$6B total; ~$4B data center portion

Claim classification: official_estimate_or_forecast · Verification: source_backed_unverified · Retrieved: 2026-09-13

Limitation: Advocacy tracker; investment split not confirmed by the developer.

Open source 1

Sources

Evidence and provenance

Open MO state research →

White Cloud Acres Data Center Project | Maryville (southern Nodaway County) | Compute Equity Atlas