CORROBORATED
Industry records place the Yondr Loudoun campus on Youngwood Lane in Aldie
Key data: 24171 Youngwood Ln, Aldie, VA 20105
Limitation: Parcel ID and lat-long not published; Loudoun County parcel records were not retrieved
This canonical record consolidates 6 source-backed observations without discarding aliases, limitations or unresolved dimensions.
| Operator / developer | Yondr (air site name) |
|---|---|
| Jurisdiction | Loudoun County / Aldie, VA |
| Address | 24171 Youngwood Ln, Aldie, VA 20105 |
| Location precision | street address |
| Coordinates | null, null |
| Capacity | Not established |
| Aliases | Yondr Data Center (Loudoun DC1) |
| Project profile | 5 rows |
|---|---|
| Intent / permits | 1 rows |
| Civic / infrastructure | 0 rows |
Industry records place the Yondr Loudoun campus on Youngwood Lane in Aldie
Key data: 24171 Youngwood Ln, Aldie, VA 20105
Limitation: Parcel ID and lat-long not published; Loudoun County parcel records were not retrieved
The project owner of record is a Yondr single-purpose entity; a directory separately lists the underlying land holder
Key data: Yondr JK 2 LLC as owner; "JK Land Holdings" listed as land owner in a separate directory
Limitation: Two directories give different owner names; no recorded deed or Virginia SCC filing was retrieved to reconcile them
Electric service is attributed to the incumbent Virginia utility
Key data: Dominion Energy
Limitation: No interconnection agreement, substation name or SCC case number published
The site sits inside the Loudoun hyperscale cluster with immediate hyperscaler neighbors
Key data: Neighboring Microsoft campus on Growth Mindset Lane and an AWS presence
Limitation: Substations, transmission lines, water/sewer mains, rail and fiber not itemized
NOT_FOUND — searched project directories and county planning pages; no water utility, water agreement or named Loudoun Economic Development contact was published for this specific project
Limitation: Loudoun Water and Loudoun Economic Development are the presumptive bodies by jurisdiction but were not confirmed on a fetched page
Status date: Permit issuance date 08/13/2026
Limitation: DEQ table gives no address, MW, or generator count; individual permit PDF not fetched.