OPERATOR
Amazon Data Services New Carlisle
St. Joseph County
AWS operates the campus (branded Project Rainier); the complex exclusively trains and runs Anthropic models.
Key data: Amazon Web Services (operator); Anthropic (exclusive workload)
CORROBORATEDLimitation: n.a.
Open source →
POWER SUPPLIER
Amazon Data Services New Carlisle
St. Joseph County
Indiana Michigan Power (AEP subsidiary) serves the campus, expected to draw more than 2.2 GW; AEP is building the Larrison Drive and New Prairie 345 kV delivery substations for ~1.1 GW of initial service by December 2026, with an I&M interconnection station authorization of $68 million.
Key data: Indiana Michigan Power (AEP); 2.2+ GW; Larrison Drive & New Prairie 345 kV substations; $68M interconnection station
CORROBORATEDLimitation: No IURC cause number for the I&M large-load contract confirmed in fetched sources.
Open source →
WATER SUPPLIER
Amazon Data Services New Carlisle
St. Joseph County
The Town of New Carlisle supplies water from two plants (~16 MGD firm, up to 18 MGD) drawing a shallow unconfined aquifer near the Kankakee headwaters; St. Joseph County adopted a voluntary 24 MGD cap for the Indiana Enterprise Center, with both major projects expected to stay under 21 MGD. Groundwater withdrawal for dewatering was approved at an additional 31 MGD for 546 days.
Key data: Town of New Carlisle water utility; ~16–18 MGD firm capacity; county 24 MGD voluntary cap; 31 MGD dewatering approval
CORROBORATEDLimitation: No numbered water service agreement located; dewatering permit ID not captured.
Open source →
JURISDICTION STACK
Amazon Data Services New Carlisle
St. Joseph County
Authorities include the Town of New Carlisle, Olive Township, St. Joseph County (Board of Commissioners, County Council, Redevelopment Commission, Drainage Board), the Indiana Enterprise Center overlay, IDEM, IURC and IDNR; the state IEDC provides incentives.
Key data: Town of New Carlisle; Olive Twp; St. Joseph County Redevelopment Commission/Council/Commissioners; Drainage Board; IDEM; IURC; IDNR; IEDC
VERIFIED PRIMARYLimitation: n.a.
Open source →
PLANNING ZONING CONTACT
Amazon Data Services New Carlisle
St. Joseph County
Planning authority for unincorporated county land and the Town of New Carlisle rests with the St. Joseph County Area Plan Commission, whose staff directory is published.
Key data: Area Plan Commission, 227 W. Jefferson Blvd, 11th Fl., South Bend, IN 46601; 574-235-7800; Executive Director Shawn Klein, AICP; planners Faryal Sharif, Adi'a Smith
VERIFIED PRIMARYLimitation: No case-specific case manager for the Amazon campus published; staff emails not listed.
Open source →
ECON DEV CONTACT
Amazon Data Services New Carlisle
St. Joseph County
The St. Joseph County Office of Economic Development leads locally with the IEDC at state level; the county's executive director of economic development is named in coverage.
Key data: Bill Schalliol, Executive Director of Economic Development, St. Joseph County; IEDC
CORROBORATEDLimitation: No email/phone published in fetched sources.
Open source →
GENERAL CONTACT
Amazon Data Services New Carlisle
St. Joseph County
The utility's community affairs manager is the named public-facing contact identified in coverage; IDEM notices provide the state permit channel.
Key data: Mona Livingston, Community Affairs Manager, Indiana Michigan Power
CORROBORATEDLimitation: No phone/email published; no Amazon community-relations contact found.
Open source →
SURROUNDING INFRASTRUCTURE
Amazon Data Services New Carlisle
St. Joseph County
The campus sits ~0.7 mi from 345 kV transmission and ~1 mi from the Kankakee River, drains via Niespodziany Ditch, adjoins the GM/Samsung SDI battery plant and Bendix Woods County Park, and is bounded by SR 2, US 20, Willow/Walnut and Smilax/Snowberry Roads.
Key data: 345 kV line ~0.7 mi; Niespodziany Ditch; SR 2 / US 20; GM-Samsung battery plant adjacent
CORROBORATEDLimitation: Tracker-derived distances; fiber routes not documented.
Open source →
EXACT LOCATION
Amazon / Hobart data centers (permit 089-50590-00739, 782 generators)
Lake County (Hobart)
The campus is at the intersection of 61st Avenue and Colorado Street in Hobart: a 168-acre "Hobart Data Center Campus" lot plus a second "Hobart Tech Park" plan south of 61st Avenue and east of Colorado Street, totaling more than 725–750 acres.
Key data: 61st Ave & Colorado St, Hobart, IN 46342; tracker address 4751 E 61st Ave; 168-acre first lot, ~725 acres total
CORROBORATEDLimitation: Street address (4751 E 61st Ave) comes from a tracker, not a permit; no parcel IDs verified.
Open source →
OWNERSHIP CHAIN
Amazon / Hobart data centers
Lake County (Hobart)
Zoning and site plans moved through Hobart Devco, LLC; project documents and trackers identify Hobart Owner LLC as the campus entity with Amazon Data Services as the air-permit applicant.
Key data: Hobart Devco, LLC (developer/rezoning); Hobart Owner LLC (campus entity); Amazon Data Services (air applicant)
CORROBORATEDLimitation: Registered-agent/parent filings for Hobart Devco and Hobart Owner LLC not retrieved; attorney Todd Leeth represents Hobart Devco.
Open source →
OPERATOR
Amazon / Hobart data centers
Lake County (Hobart)
AWS is the announced operator/end user of the campus, tied to a $15 billion Amazon investment in Hobart.
Key data: Amazon Web Services
CORROBORATEDLimitation: Tracker-sourced investment figure.
Open source →
POWER SUPPLIER
Amazon / Hobart data centers
Lake County (Hobart)
NIPSCO will supply the campus, ramping to 2,400 MW by end-2032 with service starting 2027; IURC Cause No. 46322 approved the NIPSCO–Amazon special contract and a NIPSCO–GenCo PPA, and MISO Project 51141 covers a 1,500 MW "New Hobart Load Addition."
Key data: NIPSCO; IURC Cause No. 46322; MISO Project 51141; 2,400 MW by 2032
VERIFIED PRIMARYLimitation: Repository is a community-maintained aggregation of primary filings; docket numbers not independently re-fetched from IURC/MISO this session.
Open source →
WATER SUPPLIER
Amazon / Hobart data centers
Lake County (Hobart)
NOT_FOUND for a named water utility. The developer told the plan commission the buildings "would not need water"; a tracker estimates ~14 million gallons/year for water-based cooling.
Key data: No supplier named; ~14 M gal/yr (tracker estimate)
DISCOVERY LEADLimitation: City of Hobart utilities role not documented in fetched sources.
Open source →
JURISDICTION STACK
Amazon / Hobart data centers
Lake County (Hobart)
The City of Hobart controls zoning (Plan Commission, City Council, Board of Public Works and Safety); state/federal authorities include IURC, MISO, IDEM and USACE; the site is in Lake County.
Key data: City of Hobart (Plan Commission, Council, BPW); IURC; MISO; IDEM; USACE
CORROBORATEDLimitation: n.a.
Open source →
PLANNING ZONING CONTACT
Amazon / Hobart data centers
Lake County (Hobart)
Authority rests with the Hobart Plan Commission; the city's published directory gives the Planning & Zoning Department phone but no named case manager for this project.
Key data: City of Hobart Planning & Zoning / Plan Commission, 414 Main St., Hobart, IN 46342 — 219-942-7985
VERIFIED PRIMARYLimitation: No named planner or email published for the data-center cases.
Open source →
ECON DEV CONTACT
Amazon / Hobart data centers
Lake County (Hobart)
The city publishes an Economic Development phone line in its staff directory; no named individual tied to the Amazon project was found.
Key data: City of Hobart Economic Development — 219-942-5517
VERIFIED PRIMARYLimitation: No county-level (Lake County) EDC contact found for this project.
Open source →
GENERAL CONTACT
Amazon / Hobart data centers
Lake County (Hobart)
NOT_FOUND for a project-specific PIO or company community-relations contact; the general city permitting numbers are the only channels identified (Building 219-942-1722, Zoning 219-942-7985).
Key data: City of Hobart Building Dept. 219-942-1722
CORROBORATEDLimitation: Amazon side contact not published in fetched sources.
Open source →
SURROUNDING INFRASTRUCTURE
Amazon / Hobart data centers
Lake County (Hobart)
Records reference a New Hobart 345 kV load addition and related transmission/generation, gas-fired generation and battery storage; a tracker puts the nearest 345 kV line ~0.7 mi away and Sprout Ditch ~0.9 mi; the Hobart Board of Works adopted a construction traffic plan.
Key data: New Hobart 345 kV load addition; 345 kV line ~0.7 mi; Sprout Ditch
CORROBORATEDLimitation: Water/sewer trunk lines and fiber routes not documented.
Open source →
EXACT LOCATION
Sabey Decatur Technology Park (2025-CAP-856 / 2025-CVR-856)
Marion County (Indianapolis, Decatur Twp)
The ~130-acre site is at the northeast corner/intersection of Kentucky Avenue (SR-67) and Camby Road in Decatur Township, inside the existing industrially zoned Decatur Technology Park, directly across from an AES substation.
Key data: Kentucky Ave (SR-67) & Camby Road, Decatur Township, Indianapolis; ~130 acres
CORROBORATEDLimitation: No street number or parcel ID published; project site plan uses access from SR-67 and Camby Road.
Open source →
OWNERSHIP CHAIN
Sabey Decatur Technology Park
Marion County
The petitioner is Sabey Data Center Properties LLC, a division of Seattle-based Sabey Corporation; Sabey Data Centers is jointly owned by Sabey Corporation and institutional clients managed by National Real Estate Advisors (some accounts affiliated with the IBEW).
Key data: Sabey Data Center Properties LLC → Sabey Corporation + National Real Estate Advisors-managed clients
VERIFIED PRIMARYLimitation: Land-title holder for the 130 acres not identified in fetched sources.
Open source →
OPERATOR
Sabey Decatur Technology Park
Marion County
Sabey designs, builds and operates its data centers; the Decatur facility is a colocation project intended to lease space to multiple tenants, with no tenant named.
Key data: Sabey Data Centers (operator); colocation, tenants unnamed
CORROBORATEDLimitation: n.a.
Open source →
POWER SUPPLIER
Sabey Decatur Technology Park
Marion County
AES Indiana is the electric supplier; the plan includes a 10-acre on-site substation ramping to 250 MW over five years, with initial utility upgrades anticipated by Q4 2027 and Sabey funding transmission/distribution costs.
Key data: AES Indiana; 10-acre substation; 250 MW over 5 years
VERIFIED PRIMARYLimitation: No IURC cause number or special contract ID published.
Open source →
WATER SUPPLIER
Sabey Decatur Technology Park
Marion County
The project website names Citizens Water as supplier, with a closed-loop design requiring a one-time 1,000,000-gallon fill (500,000 gal per building, 2028 and 2030) and 200,000–300,000 gallons/year ongoing.
Key data: Citizens Water (Citizens Energy Group); 1.0 M gal initial fill; 200–300k gal/yr
VERIFIED PRIMARYLimitation: Developer-published figures; no service agreement number.
Open source →
JURISDICTION STACK
Sabey Decatur Technology Park
Marion County
Land-use authority is the consolidated City of Indianapolis/Marion County Metropolitan Development Commission (with hearing examiner) covering Decatur Township; IURC governs utility investment; litigation is pending in Marion Superior Court.
Key data: Metropolitan Development Commission (MDC) + hearing examiner; Decatur Township; IURC; Marion Superior Court
CORROBORATEDLimitation: City-County Council did not vote on the variance.
Open source →
PLANNING ZONING CONTACT
Sabey Decatur Technology Park
Marion County
The MDC hearing examiner who recommended approval is named, as are counsel for both sides.
Key data: Judy Weerts Hall, MDC Hearing Examiner; Mindy Westrick Brown (Sabey counsel); Laureen White (residents' counsel)
CORROBORATEDLimitation: No department phone/email captured for the case file.
Open source →
ECON DEV CONTACT
Sabey Decatur Technology Park
Marion County
Indy Economic Development Inc. (with prior Indy Chamber endorsement) backs the project and is working with Sabey on a tax abatement; a spokesperson and attorney are named in coverage.
Key data: Indy Economic Development Inc.; spokesperson Aliya Wishner; attorney Doug Brown
CORROBORATEDLimitation: Roles/titles partially garbled in source text; no direct contact details.
Open source →
GENERAL CONTACT
Sabey Decatur Technology Park
Marion County
The project website states a dedicated community liaison exists for inquiries, but no name, phone or email was published on the fetched page.
Key data: Community liaison referenced, unnamed
DISCOVERY LEADLimitation: NOT_FOUND for an actual phone/email; legal notices are posted separately as PDFs.
Open source →
SURROUNDING INFRASTRUCTURE
Sabey Decatur Technology Park
Marion County
An AES substation sits across the street, a 10-acre substation is planned on site, access is from SR-67/Kentucky Avenue and Camby Road with 200-foot residential buffers; nearest 345 kV line ~1.1 mi and Seerley Creek ~1.0 mi.
Key data: AES substation across street; 345 kV ~1.1 mi; Seerley Creek ~1.0 mi
CORROBORATEDLimitation: Fiber and sewer trunk detail not documented.
Open source →
EXACT LOCATION
Metrobloks (tax abatements 2026-A-016/017)
Marion County (Indianapolis, Martindale-Brightwood)
The site is the ~14-acre former Sherman Drive-In theater property in Martindale-Brightwood, vacant since 1983.
Key data: 2505 N. Sherman Drive, Indianapolis; ~13–14 acres
CORROBORATEDLimitation: No parcel ID published; address sometimes given as "N. Sherman Ave."
Open source →
OWNERSHIP CHAIN
Metrobloks
Marion County
NOT_FOUND. Fetched trade coverage, trackers, local reporting and metrobloks.com (which returned no usable content) — no land owner, parent company or registered agent for Metrobloks' Indianapolis entity was published.
Key data: n.a. (developer Metrobloks; CEO named Ernest/Earnest Popescu)
DISCOVERY LEADLimitation: Company website content not extractable; CEO name spelled inconsistently across sources.
Open source →
OPERATOR
Metrobloks
Marion County
Metrobloks is described as both developer and operator of the metro-edge AI-ready facility (site code IND A1), 72–75 MW at buildout.
Key data: Metrobloks (IND A1); 72–75 MW
CORROBORATEDLimitation: No tenant named.
Open source →
POWER SUPPLIER
Metrobloks
Marion County
Public radio reporting states the facility would draw electricity through contracts with AES Indiana rather than from the residential grid.
Key data: AES Indiana (contracted supply)
CORROBORATEDLimitation: No contract ID or IURC cause number published.
Open source →
WATER SUPPLIER
Metrobloks
Marion County
A closed-loop cooling system is planned: ~19,000 gallons to fill the first building and ~47,500 gallons for the second, recirculated rather than consumed. No water utility is named.
Key data: ~19,000 gal (bldg 1) + ~47,500 gal (bldg 2), closed loop
CORROBORATEDLimitation: Supplier name NOT_FOUND (Citizens Energy Group not confirmed for this site).
Open source →
JURISDICTION STACK
Metrobloks
Marion County
The Metropolitan Development Commission approved the rezoning (April/May 2026) and the City-County Council was engaged on the project and on a temporary stay for high-impact data centers; the site is in Indianapolis/Marion County.
Key data: MDC; Indianapolis City-County Council; Marion County
CORROBORATEDLimitation: Tax abatement cases 2026-A-016/017 were not directly fetched this session.
Open source →
PLANNING ZONING CONTACT / ECON DEV CONTACT
Metrobloks
Marion County
NOT_FOUND for named staff. Coverage identifies the MDC as the deciding body and City-County Councilor Ron Gibson as the area representative, but no planner, case manager or economic-development officer was named for this project.
Key data: Councilor Ron Gibson (district representative)
DISCOVERY LEADLimitation: Abatement petitions handled through Indianapolis DMD; staff not named in fetched sources.
Open source →
GENERAL CONTACT
Metrobloks
Marion County
NOT_FOUND. The only project-side contact identified is the CEO by name; reporters noted Metrobloks did not respond to email inquiries and the corporate site returned no extractable contact information.
Key data: Metrobloks CEO Ernest Popescu (no phone/email published)
DISCOVERY LEADLimitation: metrobloks.com and /about-us returned no content on fetch.
Open source →
SURROUNDING INFRASTRUCTURE
Metrobloks
Marion County
The site is a decades-vacant brownfield at 25th Street and Sherman Drive; a company-aligned listing notes it is less than 4.7 miles from the FD-IX Internet Exchange Point with ~0.21 ms latency and carrier-neutral connectivity.
Key data: FD-IX Internet Exchange <4.7 mi; 25th St & Sherman Dr
CORROBORATEDLimitation: Substation/transmission and sewer detail not published.
Open source →
EXACT LOCATION
Blue Power LLC
Clay County (near Brazil / Carbon)
Permit documents show four adjoining plats totaling 27.62 acres off East County Road 1350 North just south of Carbon, with Brazil listed as the mailing city.
Key data: 4 plats, 27.62 acres, E. CR 1350 N, south of Carbon (Brazil, IN)
CORROBORATEDLimitation: Permit itself not fetched directly; no parcel IDs.
Open source →
OWNERSHIP CHAIN
Blue Power LLC
Clay County
Blue Power LLC owns the four adjoining plats and is the renamed successor of Claybridge Energy LLC, previously Midwest Gas Storage, Inc.; its CEO is Illinois-based Terry O'Malley.
Key data: Blue Power LLC (formerly Claybridge Energy LLC, formerly Midwest Gas Storage, Inc.); CEO Terry O'Malley
CORROBORATEDLimitation: Ultimate beneficial owner/parent above Blue Power LLC not identified; no Secretary of State filing fetched.
Open source →
OPERATOR
Blue Power LLC
Clay County
NOT_FOUND. The data-center user is unidentified: Blue Power's IDEM permit covers a combined-cycle power plant that would provide dedicated power to a nearby data center, but no data-center operator has been disclosed.
Key data: Data center operator undisclosed
DISCOVERY LEADLimitation: Project is disclosed only through the power-plant permit.
Open source →
POWER SUPPLIER
Blue Power LLC
Clay County
Power would come from Blue Power's own behind-the-meter combined-cycle plant rather than a named utility; a tracker lists WVPA / Parke County REMC as grid context and 400 MW capacity.
Key data: Self-supply via Blue Power combined-cycle plant; tracker: WVPA/Parke County REMC, 400 MW
DISCOVERY LEADLimitation: Utility attribution is tracker-sourced and unconfirmed; no interconnection/docket reference found.
Open source →
WATER SUPPLIER
Blue Power LLC
Clay County
NOT_FOUND. Searched IDEM-related coverage and county meeting reporting; no water utility, well field or agreement has been disclosed for the Clay County project.
Key data: n.a.
DISCOVERY LEADLimitation: n.a.
Open source →
JURISDICTION STACK
Blue Power LLC
Clay County
IDEM's Office of Air Quality issued the significant source modification permit; Clay County Commissioners and County Council are the local bodies, but the county has no zoning laws and says it cannot impose a moratorium; IDNR was cited as another avenue for residents.
Key data: IDEM OAQ; Clay County Commissioners & Council (no county zoning); IDNR
CORROBORATEDLimitation: The absence of county zoning is a key jurisdictional gap.
Open source →
PLANNING ZONING CONTACT
Blue Power LLC
Clay County
NOT_FOUND (structurally): Clay County has no zoning ordinance, so no planning/zoning case authority exists. Permit paperwork listed local officials as notified contacts, with a reported email/phone mismatch.
Key data: Listed officials: Patricia Heffner (Brazil Council At-Large), Mayor Brian Wyndham, Commissioner Bryan Allender
CORROBORATEDLimitation: Reporting notes the contact email/phone listed for one official actually belonged to a different person (Shane Litz).
Open source →
ECON DEV CONTACT / GENERAL CONTACT
Blue Power LLC
Clay County
NOT_FOUND. Searched for a Clay County economic development contact and any company contact; only the CEO's name was published, and the county announcements page returned no relevant content.
Key data: n.a.
DISCOVERY LEADLimitation: No EDC or PIO identified for this project.
Open source →
SURROUNDING INFRASTRUCTURE
Blue Power LLC
Clay County
NOT_FOUND for detailed infrastructure. The only located context is the site's position south of Carbon off E. CR 1350 N on former gas-storage land (Midwest Gas Storage lineage), implying gas infrastructure.
Key data: E. CR 1350 N; former gas-storage site lineage
DISCOVERY LEADLimitation: No substation, pipeline, water/sewer or fiber specifics published.
Open source →