Compute Equity Atlas
← National map
Indiana / IN

Indiana data center and compute infrastructure map

Start with the state view and mapped project locations, then move into permits, planning, civic context, operators and source evidence. Only locations supported by explicit coordinates are plotted.

0mapped locations
98deep evidence rows
7validated refresh rows
Animated state view

Indiana

True aspect · centered · uncropped
Evidence-backed project locations

Indiana project points

Only records with explicit published coordinates are plotted here. Missing coordinates remain visible in the evidence sections rather than being guessed.

0 mapped locations
No project in this state currently has coordinates strong enough to plot. The state evidence below remains available while location proof is compiled.
ProjectsIntent signalsCivic impactProject profilesInfrastructureSources & gaps
Current development signals

Permits, filings, zoning and other activity

6 source-backed evidence rows are integrated on this page.

New stationary data center at 1598 W SR 42, Mooresville, IN 46158 (Woodland Caribou LLC)

Morgan County / Mooresville (Monroe Township)

Developer / operator: Woodland Caribou LLC

Status: "Notice of 30-Day Period for Public Comment"; "Preliminary Findings"; proposed permit "would allow Woodland Caribou LLC to construct and operate a new stationary data center if approved by IDEM's Office of Air Quality"

Permit / docket: Part 70 Operating Permit No. T109-50085-00094

Record type: New Source Construction and Part 70 Operating Permit

VERIFIED PRIMARY

Limitation: Local reporting links this Monroe Township site to Google; the IDEM notice names only Woodland Caribou LLC, so operator is reported exactly as filed. No MW/sq ft in the notice.

Open source →

Amazon Data Services, Inc. facility (New Carlisle area, per IDEM public-notice listing by county)

St. Joseph County

Developer / operator: Amazon Data Services, Inc.

Status: "NPDES Draft Permit Public Notice"; public comment open

Permit / docket: Permit No. 141-50312-00650

Record type: NPDES Draft Permit (wastewater discharge)

VERIFIED PRIMARY

Limitation: The IDEM listing does not use the phrase "data center" for this entry; facility name and county are as listed.

Open source →

Two adjacent Hobart data center sites treated as one source (26 buildings)

Lake County / Hobart

Developer / operator: Amazon Data Services (application prepared by Ramboll)

Status: IDEM lists the permit as "Initial Processing"; "No draft or issued permit is shown"

Permit / docket: IDEM Permit 089-50590-00739

Record type: New Source Minor PSD/Emission Offset construction approval and FESOP (air permit application)

Capacity / size: 782 diesel generators totaling 2,119 MW; ~5.47 million gallons of listed tank capacity

CORROBORATED

Limitation: Could not reach the IDEM permit-status record itself this session (CAATS/permit-status search is an interactive portal). Generator/MW figures are from the republished application, not an issued permit.

Open source →

Decatur Technology Park data center — various addresses 6700–8210 Camby Rd & 6600–6833 Kentucky Ave; East Building A and West Building B

Marion County / Indianapolis (Decatur Township)

Developer / operator: Sabey Data Center Properties, LLC (rep. Mindy Westrick Brown)

Status: Legal notice of public hearing before the Metropolitan Development Commission; site plan and elevations "filed December 29, 2025"; proposed data center technology park use stated as "not permitted" under the ordinance

Permit / docket: 2025-CAP-856 / 2025-CVR-856 (Amended); modifies commitments from 2020-CZN-834

Record type: Modification of Commitments plus Variance of Use and Development Standards (Consolidated Zoning and Subdivision Ordinance)

Capacity / size: Building heights 30 ft (A) and 50 ft (B), variance sought for >50 ft up to 75 ft; 200 parking spaces requested; acreage not stated in the notice

VERIFIED PRIMARY

Limitation: Notice is the petitioner-hosted copy of the MDC legal notice. Later approval (reported March 2026) and the resident lawsuit were not confirmed from a court or MDC record in this session.

Open source →

Data center at 2505 North Sherman Drive, Council District #8

Marion County / Indianapolis (Center Township)

Developer / operator: Metrobloks, LLC

Status: "For Public Hearing"; "recommend approval of ten (10) years real property tax abatement" and "fifteen (15) years enhanced personal property tax abatement"; "request will be made to continue to August 19, 2026"

Permit / docket: 2026-A-016 (real property) and 2026-A-017 (enhanced personal property); related rezoning petitions 2025-ZON-124 / 2025-VAR-012

Record type: Final Economic Revitalization Area Resolution (tax abatement); rezoning of 13.68 acres I-2 → C-S

Capacity / size: 13.68 acres (rezoning petition); MW not stated

VERIFIED PRIMARY

Limitation: Rezoning case numbers 2025-ZON-124 / 2025-VAR-012 and the 13.68-acre figure appear in MDC hearing-examiner agenda search results, not in the August 5 agenda I fetched; the abatement resolutions are verified from the fetched agenda.

Open source →

Power generation project associated with a potential data center development, 499 E CR 1350 N, Brazil, IN 47834

Clay County / near Brazil (south of Carbon)

Developer / operator: Blue Power LLC

Status: IDEM "granted an air permit to Blue Power LLC for a power generation project" (per local reporting); permitted-sources listing shows issued 2025-09-24, expiring 2030-09-24

Permit / docket: 18-021-00020 (source ID 48829), Title V ("TV")

Record type: Air permit (Title V), listed "Operating"

DISCOVERY LEAD

Limitation: The permit ID, dates and address were read from the search-index snippet of the IDEM permitted-sources spreadsheet; I did not successfully open the spreadsheet itself this session, and the data-center connection is asserted by local reporting, not by the permit record.

Open source →

Civic and infrastructure context

What the evidence says around these projects

34 source-backed evidence rows are integrated on this page.

ENVIRONMENTAL JUSTICE DEMOGRAPHIC

Metrobloks

Marion County (Indianapolis — Martindale Brightwood)

The Metrobloks site is the former Sherman Drive-In in Martindale Brightwood, a historically Black east-side Indianapolis neighborhood, and the EJ framing of the incentive debate turns on siting a ~$500 million, ~14-acre data center in that community.

Key data: Site: 2505 N. Sherman Drive, historically Black Martindale Brightwood; ~14 acres; ~$500M project

CORROBORATED

Limitation: Qualitative EJ characterization; no tract percentile or index score located

Open source →

ENVIRONMENTAL JUSTICE DEMOGRAPHIC

NOT_FOUND — quantitative EJ screening for IN sites

Statewide

Searched for EJScreen percentiles or an Indiana state EJ mapping equivalent for Mooresville/Morgan County, New Carlisle/St. Joseph County, Hobart/Lake County, Decatur Township, Martindale Brightwood and Clay County. EPA EJScreen is offline as of February 5, 2025, and no Indiana state EJ screening tool with published tract percentiles was located.

Key data: No Indiana state EJ screening tool with percentile outputs identified

DISCOVERY LEAD

Limitation: IDEM does not publish an EJScreen-equivalent percentile tool that was retrievable this session

Open source →

WATER WITHDRAWAL VOLUME

Amazon Data Services

St. Joseph County (New Carlisle)

The St. Joseph County Drainage Board approved construction-site dewatering discharge of up to 31 million gallons per day into the Niespodziany Ditch from the southwest corner of the property, reduced from Amazon's requested 35 MGD. Monitoring devices will track ditch water levels and the board can suspend dewatering. Neighboring farmers pushed back over planting-season impacts; Amazon issued a "letter of commitment" to engage in good faith on landowner concerns.

Key data: 31 MGD dewatering discharge approved (35 MGD requested)

CORROBORATED

Limitation: This is construction dewatering discharge, not operational cooling withdrawal; article gives no calendar date

Open source →

WATER WITHDRAWAL VOLUME

Amazon Data Services — Section 401 certification

St. Joseph County (New Carlisle)

The Section 401 Water Quality Certificate for the New Carlisle campus covers impacts to 9.7 acres of wetlands and over 5,000 feet of streams in the Kankakee River watershed, adjacent to Bendix Woods Nature Preserve. Comment deadline was April 30, 2025.

Key data: 9.7 acres wetlands; >5,000 feet of streams impacted

DISCOVERY LEAD

Limitation: Advocacy summary of an IDEM notice; certificate number not stated (notice filename references 2025-78-71-enh-wqc)

Open source →

WATER WITHDRAWAL VOLUME

Woodland Caribou LLC / Project Louie (Google)

Morgan County (Monrovia / Mooresville)

Documents in a pending IURC case indicate the campus is expected to use roughly 4 million gallons per day — about three times the electricity and four times the water of a comparable proposed Franklin Township project. One report attributes the ~4 MGD figure to per-building maximum capacity.

Key data: ~4 million gallons/day expected water use

CORROBORATED

Limitation: Sources disagree on whether 4 MGD is campus-wide or per building; at the October 2025 plan commission hearing the developer provided no water-use volume, source or wastewater figure

Open source →

WATER WITHDRAWAL VOLUME

Sabey Decatur Technology Park

Marion County (Decatur Township)

Reporting on the project records a 1 million gallon groundwater startup fill plus 200,000–300,000 gallons per year of routine use, consistent with the closed-loop cooling design Sabey advertises.

Key data: 1M gal startup fill; 200,000–300,000 gal/yr routine

DISCOVERY LEAD

Limitation: Advocacy source; company-side confirmation limited to a general closed-loop claim on the project website

Open source →

UTILITY INTERCONNECTION QUEUE

IURC Cause No. 46097 — I&M large load tariff

Statewide

The IURC issued its large-load order in Cause 46097 on February 19, 2025, setting a 70 MW individual threshold (150 MW aggregate). Parties included I&M, the OUCC, Citizens Action Coalition, Amazon Data Services, Google, Microsoft and the Data Center Coalition.

Key data: 70 MW individual / 150 MW aggregate threshold; order dated 2025-02-19

VERIFIED PRIMARY

Limitation: Applies to I&M service territory; Hobart (NIPSCO) and Indianapolis (AES Indiana) loads sit outside this tariff

Open source →

UTILITY INTERCONNECTION QUEUE

NIPSCO GenCo, IURC Cause 46183

Northern Indiana (Lake / LaPorte / Michigan City)

NIPSCO received Commission approval for NIPSCO GenCo as a public utility to serve large loads, isolating large-customer risk contractually, with roughly 3 GW of capacity to be added. Listed projects include AWS and Google in northern Indiana, Google Michigan City (300 MW) and Microsoft LaPorte (538 MW).

Key data: ~3 GW to be added via NIPSCO GenCo; Cause 46183

VERIFIED PRIMARY

Limitation: Industry-association compilation; individual docket orders not fetched

Open source →

UTILITY INTERCONNECTION QUEUE

Project Louie (Google) — AES Indiana agreement

Morgan County

EEI records the AES Indiana / Google Morgan Township data center at 390 MW, with the agreement expected to deliver $770 million in savings to existing customers over 15 years. A planned 1,200 MW substation is documented for the site, and at 90% capacity annual consumption would approach twice the 2024 usage of all AES Indiana residential customers combined.

Key data: 390 MW contracted (EEI); 1,200 MW planned substation; ~2x all AES Indiana residential usage at 90% capacity

VERIFIED PRIMARY

Limitation: 390 MW (contract) and 1,200 MW (substation) are different measures and should not be conflated

Open source →

COMMUNITY OPPOSITION OR LITIGATION

Sabey Decatur Technology Park

Marion County (Decatur Township)

Seven Decatur Township residents, represented by attorney Arie J. Lipinski, sued in Marion County Superior Court to block the project, arguing the Metropolitan Development Commission's March 2026 approval of a variance of use rather than a rezoning amounted to illegal variances and a "disguised rezoning." Sabey filed a motion to dismiss on June 15, with a status conference on June 29.

Key data: 7 plaintiffs; Marion County Superior Court; motion to dismiss filed 2026-06-15

CORROBORATED

Limitation: Case number not stated in fetched sources

Open source →

COMMUNITY OPPOSITION OR LITIGATION

Amazon / Hobart data center campus

Lake County (Hobart)

Four residents — Angelita Soriano, Albina Venegas-Roman, Barbara Koteles and Joseph Conn — sued the Hobart Plan Commission and Common Council on December 8, 2025 in Lake Superior Court (case 45D11-2512-MI-000644) over the rezoning of roughly 700 acres from R-3 to M-1 (155 acres of it in 2022). A preliminary-injunction motion followed on February 5, 2026 concerning a November 6, 2025 fill permit.

Key data: Case 45D11-2512-MI-000644 filed 2025-12-08; ~700 acres rezoned R-3 → M-1

CORROBORATED

Limitation: Docket status after February 2026 not confirmed

Open source →

COMMUNITY OPPOSITION OR LITIGATION

Metrobloks abatements 2026-A-016 / 017

Marion County (Martindale Brightwood)

The MDC hearing on the $56 million incentive package was postponed from August 5 to August 19, 2026 at the city's request so community commitments could be finalized. Residents said the company's commitments would not be enough to make an impact. The city's own Department of Metropolitan Development director, Megan Vukusich, opposed the package on July 15.

Key data: Hearing moved 2026-08-05 → 2026-08-19; DMD director opposed the package

CORROBORATED

Limitation: Final vote outcome not stated in any fetched source

Open source →

Show all remaining 22 evidence rows
COMMUNITY OPPOSITION OR LITIGATION

Project Louie (Google)

Morgan County

Terri Moore and another nearby property owner sued in March 2025 seeking judicial review of the February 2025 rezoning of 390.74 acres; a second resident (Dill) filed suit that was consolidated with Moore's in January of the following year, and litigation remained ongoing. Roughly 200 people attended the October 2025 plan commission meeting; more than 250 attended a February 2025 town hall.

Key data: Consolidated rezoning litigation ongoing; ~200 attendees Oct 2025, >250 Feb 2025

CORROBORATED

Limitation: Case numbers and court not stated; student-newsroom investigation

Open source →

COMMUNITY OPPOSITION OR LITIGATION

Blue Power LLC

Clay County (near Brazil / Carbon)

IDEM granted an air permit for power generation south of Carbon without notifying county officials. Because Clay County has no zoning, it cannot impose a moratorium. Residents raised air and noise concerns at two meetings on July 6, 2026 and were exploring a referendum.

Key data: County officials not notified; no county zoning, so no moratorium possible

CORROBORATED

Limitation: Permit number not stated; planned capacity (~400 MW) sourced only from an aggregator

Open source →

RATEPAYER OR GRID IMPACT

Amazon / Hobart — ratepayer treatment

Lake County (Hobart)

Under the NIPSCO GenCo structure, cost savings for existing customers are projected at $1.25 billion, roughly $90–$115 annually per residential customer, with large-customer risk isolated contractually.

Key data: Projected $1.25B savings; ~$90–$115/yr per residential customer

VERIFIED PRIMARY

Limitation: Utility-side projection compiled by an industry association; no consumer-advocate counter-analysis fetched

Open source →

RATEPAYER OR GRID IMPACT

Sabey — AES Indiana rate impact

Marion County (Decatur Township)

The project website states existing customer rates are not expected to be negatively impacted under AES's plan and the IURC-reviewed process, and that closed-loop cooling minimizes water use. Separately, intervenor comments in AES Indiana's 2025 IRP urged the utility to run a rate analysis assuming a separate data center rate class.

Key data: Developer claim of no negative rate impact; IRP comments seek separate data center rate class

VERIFIED PRIMARY

Limitation: Developer claim is unverified; the IRP comment document is redacted

Open source →

RATEPAYER OR GRID IMPACT

NIPSCO large-load sub-docket

Statewide

The Indiana Office of Utility Consumer Counselor records that NIPSCO's electric rate case establishes a sub-docket to address issues related to new large or mega load customers, including data centers.

Key data: Sub-docket established for large/mega load customers including data centers

VERIFIED PRIMARY

Limitation: Sub-docket number and outcome not captured

Open source →

AGRICULTURAL OR LAND USE CONVERSION

Project Louie (Google)

Morgan County (Monrovia)

Approximately 550–560 acres of farmland were rezoned to Planned Unit Development in two steps: 390.74 acres approved 3-0 by the Morgan County Commissioners in February 2025, then 158 additional acres in the 1500 block of West Keller Hill Road, Monroe Township, recommended 5-2 by the Plan Commission and approved in October 2025. The land was previously farmland, houses, wetlands, streams and woodlots; petitioners were HDC Real Estate LLC and Woodland Caribou LLC (a Delaware shell company), represented by Barnes & Thornburg.

Key data: 390.74 ac (Feb 2025, 3-0) + 158 ac (Oct 2025, 5-2 recommendation) = ~550 acres of farmland converted

CORROBORATED

Limitation: Total acreage reported as 500, 550 and 560 across sources

Open source →

AGRICULTURAL OR LAND USE CONVERSION

Amazon / Hobart campus

Lake County (Hobart)

Roughly 700–723 acres were converted, with 155 acres rezoned from R-3 residential to M-1 in 2022 and the balance later; Hobart Resolution 2026-01 declared an approximately 723-acre project area an Economic Revitalization Area on January 7, 2026.

Key data: ~700 acres rezoned R-3 → M-1; ~723-acre ERA designated 2026-01-07

CORROBORATED

Limitation: Prior land use (residential vs agricultural) not specified in fetched sources

Open source →

AGRICULTURAL OR LAND USE CONVERSION

Metrobloks

Marion County (Martindale Brightwood)

This is infill redevelopment rather than farmland conversion: the ~14-acre site is the former Sherman Drive-In theater in an established urban neighborhood.

Key data: ~14 acres, former Sherman Drive-In (urban infill)

CORROBORATED

Limitation: Included to distinguish infill from greenfield conversion

Open source →

DECOMMISSIONING PROVISION

Proposed SU-47 special use district

Marion County

The SU-47 data center zoning proposal (PROP26-238) requires rezoning into a Medium Industrial (I-3) base district plus an operations plan, annual reporting and a public dashboard — but the presentation materials state that no decommissioning requirements are included.

Key data: SU-47: no decommissioning requirement stated

VERIFIED PRIMARY

Limitation: Explicit negative finding from a primary city document

Open source →

DECOMMISSIONING PROVISION

NOT_FOUND — DECOMMISSIONING_PROVISION for IN anchor projects

Statewide

Searched Hobart's resolutions 2026-01 through 2026-04, the Morgan County PUD conditions, the Marion County SU-47 proposal and the Clay County situation for decommissioning plans, bonding or site-restoration requirements. None were found; Marion County's own SU-47 materials confirm no decommissioning requirement, Morgan County's PUD conditions cover height, coverage and noise only, and Clay County has no zoning at all.

Key data: No decommissioning or financial-assurance requirement found for any IN anchor project

VERIFIED PRIMARY

Limitation: Full text of Hobart's community enhancement agreement not retrieved; a decommissioning clause could exist there

Open source →

FISCAL IMPACT LOCAL GOVERNMENT

Amazon / Hobart — incentives and payments

Lake County (Hobart)

On January 7–8, 2026 the Hobart Common Council voted 6-0 on three resolutions granting a 10-year, 100% real property tax abatement per eligible building and a 35-year, 100% enterprise IT equipment exemption, on an $11 billion project at 61st Avenue and Colorado Street. The package schedules $175 million in community enhancement contributions: $47 million upfront (due by January 31, outside the levy and outside any TIF district), then $45M, $43M and $40M at construction milestones, $10 million after the first building permit, and up to $2 million per building per year. Statement of Benefits projects 400+ permanent Amazon jobs at $37.44/hour. The mayor projected $102 million in city payments in 2026, $43M in 2027, $40M in 2028 and roughly $50M/yr after buildout. Public hearing ran two hours with only three speakers in favor.

Key data: 10-yr/100% real property abatement + 35-yr/100% IT equipment exemption; $175M community enhancement schedule; $47M upfront; 400+ jobs at $37.44/hr

CORROBORATED

Limitation: Abatement values are foregone-revenue commitments, not realized; mayor's out-year figures are projections. Sources differ on whether resolutions were adopted Jan 7 or Jan 8, 2026

Open source →

FISCAL IMPACT LOCAL GOVERNMENT

Indiana data center sales tax exemption

Statewide

Qualifying investments under $750 million may receive up to 25 years of Indiana gross retail and use tax exemption; investments over $750 million may receive up to 50 years. Local governments may separately grant an enterprise IT equipment exemption.

Key data: Up to 25 years (<$750M) or 50 years (>$750M) of state sales/use tax exemption

DISCOVERY LEAD

Limitation: Secondary compilation of statute; Indiana Code text not fetched directly

Open source →

FISCAL IMPACT LOCAL GOVERNMENT

Metrobloks abatements

Marion County (Martindale Brightwood)

Indianapolis Economic Development Inc. proposed a nearly $56 million package: $13.5 million in real property abatement over 10 years plus a $42 million equipment abatement (90% over 15 years) on roughly $406 million of equipment. A future tenant could save up to $339 million. The project is estimated to generate about $10 million per year in property tax, with a $2.5 million community pledge that could rise to $20 million.

Key data: $56M package ($13.5M real property/10 yr + $42M equipment at 90%/15 yr); ~$10M/yr projected property tax; up to $339M tenant savings

CORROBORATED

Limitation: Vote outcome unconfirmed; the $10M/yr revenue figure is a proponent projection

Open source →

FISCAL IMPACT LOCAL GOVERNMENT

Sabey Decatur Technology Park

Marion County (Decatur Township)

The project is reported at $4 billion (one source says $2 billion) on a 130-acre, ~1 million sq ft campus near Kentucky Avenue and Camby Road. Its dockets are 2025-CAP-856 / 2025-CVR-856.

Key data: $4B investment; 130 acres; ~1M sq ft

CORROBORATED

Limitation: Investment figure inconsistent between sources ($2B vs $4B); no abatement dollar value located

Open source →

FISCAL IMPACT LOCAL GOVERNMENT

Project Louie (Google) — abatement

Morgan County

The May 2025 development agreement provides that Google would pay no local taxes on qualified computing equipment for 40 years, on a $1 billion planned investment. Morgan County also adopted Economic Revitalization Area resolutions on May 27, 2025.

Key data: Zero local tax on qualified computing equipment for 40 years

CORROBORATED

Limitation: Agreement text not fetched; 40-year term reported by journalists

Open source →

NOISE OR TRAFFIC IMPACT

Proposed SU-47 noise and setback standards

Marion County

The SU-47 proposal would cap data center noise at 55 decibels and require a 400-foot setback from all residential districts, schools and churches, plus landscaping and screening, an operations plan, annual reporting and a public dashboard.

Key data: 55 dB noise cap; 400-ft setback from protected districts

VERIFIED PRIMARY

Limitation: Measurement point for the 55 dB limit not specified in the presentation

Open source →

NOISE OR TRAFFIC IMPACT

Project Louie PUD conditions

Morgan County (Monrovia)

The PUD rezoning caps noise at 65 decibels at the property line — compared in reporting to the level of a business office — limits primary buildings to 75 feet and caps hard-surface lot coverage at three-quarters.

Key data: 65 dB at property line; 75-ft height cap; 75% hard-surface coverage cap

CORROBORATED

Limitation: PUD ordinance text not fetched directly

Open source →

NOISE OR TRAFFIC IMPACT

Amazon / Hobart — traffic plan

Lake County (Hobart)

The Hobart Board of Works approved a traffic plan for the data center site on August 6, 2026. The community enhancement agreement also records commitments covering acoustics, roadway work, fire training and construction mitigation.

Key data: Traffic plan approved 2026-08-06; agreement includes acoustics and roadway commitments

CORROBORATED

Limitation: Plan contents, trip counts and decibel commitments not published in fetched sources

Open source →

CUMULATIVE REGIONAL IMPACT

Amazon / Hobart air permit application

Lake County (Hobart)

Amazon's IDEM air application, filed July 24, 2026 by Ramboll and running roughly 190 pages, covers two facilities (4751 E 61st Ave and 6197 Colorado St) with 26 buildings, 782 generators totaling 2,119 MW, 808 tanks and more than 5.46 million gallons of diesel.

Key data: 782 generators / 2,119 MW; 808 tanks; >5.46M gallons diesel across 26 buildings

CORROBORATED

Limitation: Application under review; no cumulative-impact analysis by IDEM located

Open source →

CUMULATIVE REGIONAL IMPACT

Countywide data center moratorium

Marion County

Responding to four data center proposals in a single year (Google, Metrobloks, Sabey, DC Blox), the Metropolitan Development Commission voted 6-0 in August 2026 to bar new data centers in Marion County until at least December 31, 2027, after the City-County Council voted 23-1 to advance the measure. A committee of experts and residents will study campus size, building height, environmental impacts and sound levels; Mayor Hogsett proposed $150,000 for it in the 2027 budget. Already-approved DC Blox, Metrobloks and Sabey projects are exempt, protected by state law.

Key data: Moratorium adopted 6-0; runs through at least 2027-12-31; three approved projects exempt

CORROBORATED

Limitation: Exact enactment date not stated ("Wednesday" in August 2026)

Open source →

CUMULATIVE REGIONAL IMPACT

Amazon Data Services — air permit modification 141-50312-00650

St. Joseph County (New Carlisle)

IDEM opened a 30-day comment period on a significant modification to Amazon's Part 70 operating permit at 31100 State Road 2, New Carlisle, adding two new generators and modifying existing ones, with possible Title I changes to synthetic minor emission limits. The underlying permit was issued May 1, 2025.

Key data: SPM 141-50312-00650; 2 new generators added; base permit issued 2025-05-01

VERIFIED PRIMARY

Limitation: Notice document is dated after the retrieval date in its filename (20260916), suggesting a forward-dated posting; generator capacities and emission limits are not in the notice

Open source →

CUMULATIVE REGIONAL IMPACT

Statewide moratorium demand

Statewide

Hoosier Action called for a statewide moratorium on data center construction, aggregating water, land and grid concerns across projects.

Key data: Statewide moratorium demanded

DISCOVERY LEAD

Limitation: Advocacy position, not a policy in force

Open source →

Project profile evidence

Operators, locations, power, water, capacity and other project facts

58 source-backed evidence rows are integrated on this page.

EXACT LOCATION

Woodland Caribou LLC data center (permit T109-50085-00094)

Morgan County (Mooresville/Monrovia)

IDEM's air permit notices give the facility street address; local notices describe the rezoned area bounded by Keller Hill Road, Antioch Road and State Road 42, with an initial 390.74-acre tract and ~550 acres total.

Key data: 1598 W SR 42, Mooresville, IN 46158 (Morgan County); ~391 acres initial, ~550 acres total

VERIFIED PRIMARY

Limitation: No parcel/APN numbers published in fetched notices.

Open source →

OWNERSHIP CHAIN

Woodland Caribou LLC data center

Morgan County

Investigative reporting identifies Woodland Caribou LLC as a Delaware-formed Google shell that bought 15 properties between Sept. 10 and Nov. 14, 2025 for nearly $78 million; Google publicly confirmed itself as developer.

Key data: Woodland Caribou LLC (Delaware) = Google; 15 properties, ~$78M

CORROBORATED

Limitation: No Secretary of State filing or deed instrument numbers retrieved this session.

Open source →

OPERATOR

Woodland Caribou LLC data center

Morgan County

Local reporting states the operating company had not been disclosed publicly at the time of the tax-abatement approvals; Google has since been identified as developer.

Key data: Operator not disclosed (developer Google)

DISCOVERY LEAD

Limitation: Operator/tenant identity remains formally undisclosed in permit record.

Open source →

POWER SUPPLIER

Woodland Caribou LLC data center

Morgan County

AES Indiana will provide electric service, with a planned on-site substation; AES estimated $737.3 million to power the project, and 166 diesel backup generators are proposed in the air application.

Key data: AES Indiana; planned substation; 166 backup gensets

CORROBORATED

Limitation: No IURC cause number or special-contract ID found for this load in fetched sources.

Open source →

WATER SUPPLIER

Woodland Caribou LLC data center

Morgan County

No named water utility was found; reporting states each building could use ~4 million gallons/day at maximum capacity, and the air application includes an on-site wastewater treatment plant, lift stations and booster pumps with backup generators.

Key data: ~4 MGD per building (max); on-site WWTP, lift stations, booster pumps

DISCOVERY LEAD

Limitation: Water supplier/agreement not disclosed in fetched sources (NOT_FOUND for supplier name).

Open source →

JURISDICTION STACK

Woodland Caribou LLC data center

Morgan County

Morgan County Commissioners approved rezonings and the County Council handled tax abatement; the site is in Monroe Township; IDEM Office of Air Quality issues the Part 70 permit; the Indiana Economic Development Corp. approved state incentives.

Key data: Morgan County Commissioners & County Council; Monroe Township; IDEM OAQ (Part 70 No. 109-50085-00094); IEDC

VERIFIED PRIMARY

Limitation: n.a.

Open source →

PLANNING ZONING CONTACT

Woodland Caribou LLC data center

Morgan County

The county plan director is named in investigative reporting, which also documents that she signed an NDA with the project's design consultant.

Key data: Laura Parker, Morgan County Plan Director (signed NDA with Anchor Designs LLC)

CORROBORATED

Limitation: No direct phone/email published in fetched sources.

Open source →

ECON DEV CONTACT

Woodland Caribou LLC data center

Morgan County

Morgan County Economic Development Corporation is the involved agency, with its executive director named.

Key data: Mike Dellinger, Executive Director, Morgan County EDC

CORROBORATED

Limitation: No email/phone published.

Open source →

GENERAL CONTACT

Woodland Caribou LLC data center

Morgan County

IDEM publishes a named permit contact for the air permit, which is the only general point of contact identified.

Key data: Omar El-Rjoob, IDEM Office of Air Quality — (317) 232-4971 / (800) 451-6027, oelrjoob@idem.IN.gov

VERIFIED PRIMARY

Limitation: No company-side community-relations contact found.

Open source →

SURROUNDING INFRASTRUCTURE

Woodland Caribou LLC data center

Morgan County

Site fronts State Road 42 with West Keller Hill Road, Union Church Road and Antioch Road bounding it; project includes 36 cooling towers, a planned substation, WWTP, lift stations and booster pumps; an IDEM 401 notice ties "Project Louie" wetlands work to SR 42.

Key data: SR 42; Keller Hill Rd; Antioch Rd; planned substation; 36 cooling towers

CORROBORATED

Limitation: Transmission voltage, fiber and rail access not documented.

Open source →

EXACT LOCATION

Amazon Data Services (NPDES/air permit 141-50312-00650)

St. Joseph County (New Carlisle)

The campus is ~1,200 acres in the Indiana Enterprise Center near New Carlisle in Olive Township, with local documentation citing Huckleberry Road and Gordon Road; incentive filings reference three parcels totaling 870 acres and a 640-acre tract south of State Road 2.

Key data: Huckleberry Rd & Gordon Rd, New Carlisle (Olive Township); ~1,200 acres campus; 870-acre incentive parcels

CORROBORATED

Limitation: Acreage varies by phase (600, 640, 870, 1,200); no parcel IDs verified.

Open source →

OWNERSHIP CHAIN

Amazon Data Services New Carlisle

St. Joseph County

Amazon assembled more than 600 acres of farmland around New Carlisle in 2023 through the shell entity "Razor5" and owns the land and buildings in an ~$11 billion self-build.

Key data: Shell buyer "Razor5" → Amazon Data Services; Amazon owns land + 32 buildings

DISCOVERY LEAD

Limitation: Shell-entity claim is tracker/analyst-sourced; no deed or Secretary of State record fetched.

Open source →

Show all remaining 46 evidence rows
OPERATOR

Amazon Data Services New Carlisle

St. Joseph County

AWS operates the campus (branded Project Rainier); the complex exclusively trains and runs Anthropic models.

Key data: Amazon Web Services (operator); Anthropic (exclusive workload)

CORROBORATED

Limitation: n.a.

Open source →

POWER SUPPLIER

Amazon Data Services New Carlisle

St. Joseph County

Indiana Michigan Power (AEP subsidiary) serves the campus, expected to draw more than 2.2 GW; AEP is building the Larrison Drive and New Prairie 345 kV delivery substations for ~1.1 GW of initial service by December 2026, with an I&M interconnection station authorization of $68 million.

Key data: Indiana Michigan Power (AEP); 2.2+ GW; Larrison Drive & New Prairie 345 kV substations; $68M interconnection station

CORROBORATED

Limitation: No IURC cause number for the I&M large-load contract confirmed in fetched sources.

Open source →

WATER SUPPLIER

Amazon Data Services New Carlisle

St. Joseph County

The Town of New Carlisle supplies water from two plants (~16 MGD firm, up to 18 MGD) drawing a shallow unconfined aquifer near the Kankakee headwaters; St. Joseph County adopted a voluntary 24 MGD cap for the Indiana Enterprise Center, with both major projects expected to stay under 21 MGD. Groundwater withdrawal for dewatering was approved at an additional 31 MGD for 546 days.

Key data: Town of New Carlisle water utility; ~16–18 MGD firm capacity; county 24 MGD voluntary cap; 31 MGD dewatering approval

CORROBORATED

Limitation: No numbered water service agreement located; dewatering permit ID not captured.

Open source →

JURISDICTION STACK

Amazon Data Services New Carlisle

St. Joseph County

Authorities include the Town of New Carlisle, Olive Township, St. Joseph County (Board of Commissioners, County Council, Redevelopment Commission, Drainage Board), the Indiana Enterprise Center overlay, IDEM, IURC and IDNR; the state IEDC provides incentives.

Key data: Town of New Carlisle; Olive Twp; St. Joseph County Redevelopment Commission/Council/Commissioners; Drainage Board; IDEM; IURC; IDNR; IEDC

VERIFIED PRIMARY

Limitation: n.a.

Open source →

PLANNING ZONING CONTACT

Amazon Data Services New Carlisle

St. Joseph County

Planning authority for unincorporated county land and the Town of New Carlisle rests with the St. Joseph County Area Plan Commission, whose staff directory is published.

Key data: Area Plan Commission, 227 W. Jefferson Blvd, 11th Fl., South Bend, IN 46601; 574-235-7800; Executive Director Shawn Klein, AICP; planners Faryal Sharif, Adi'a Smith

VERIFIED PRIMARY

Limitation: No case-specific case manager for the Amazon campus published; staff emails not listed.

Open source →

ECON DEV CONTACT

Amazon Data Services New Carlisle

St. Joseph County

The St. Joseph County Office of Economic Development leads locally with the IEDC at state level; the county's executive director of economic development is named in coverage.

Key data: Bill Schalliol, Executive Director of Economic Development, St. Joseph County; IEDC

CORROBORATED

Limitation: No email/phone published in fetched sources.

Open source →

GENERAL CONTACT

Amazon Data Services New Carlisle

St. Joseph County

The utility's community affairs manager is the named public-facing contact identified in coverage; IDEM notices provide the state permit channel.

Key data: Mona Livingston, Community Affairs Manager, Indiana Michigan Power

CORROBORATED

Limitation: No phone/email published; no Amazon community-relations contact found.

Open source →

SURROUNDING INFRASTRUCTURE

Amazon Data Services New Carlisle

St. Joseph County

The campus sits ~0.7 mi from 345 kV transmission and ~1 mi from the Kankakee River, drains via Niespodziany Ditch, adjoins the GM/Samsung SDI battery plant and Bendix Woods County Park, and is bounded by SR 2, US 20, Willow/Walnut and Smilax/Snowberry Roads.

Key data: 345 kV line ~0.7 mi; Niespodziany Ditch; SR 2 / US 20; GM-Samsung battery plant adjacent

CORROBORATED

Limitation: Tracker-derived distances; fiber routes not documented.

Open source →

EXACT LOCATION

Amazon / Hobart data centers (permit 089-50590-00739, 782 generators)

Lake County (Hobart)

The campus is at the intersection of 61st Avenue and Colorado Street in Hobart: a 168-acre "Hobart Data Center Campus" lot plus a second "Hobart Tech Park" plan south of 61st Avenue and east of Colorado Street, totaling more than 725–750 acres.

Key data: 61st Ave & Colorado St, Hobart, IN 46342; tracker address 4751 E 61st Ave; 168-acre first lot, ~725 acres total

CORROBORATED

Limitation: Street address (4751 E 61st Ave) comes from a tracker, not a permit; no parcel IDs verified.

Open source →

OWNERSHIP CHAIN

Amazon / Hobart data centers

Lake County (Hobart)

Zoning and site plans moved through Hobart Devco, LLC; project documents and trackers identify Hobart Owner LLC as the campus entity with Amazon Data Services as the air-permit applicant.

Key data: Hobart Devco, LLC (developer/rezoning); Hobart Owner LLC (campus entity); Amazon Data Services (air applicant)

CORROBORATED

Limitation: Registered-agent/parent filings for Hobart Devco and Hobart Owner LLC not retrieved; attorney Todd Leeth represents Hobart Devco.

Open source →

OPERATOR

Amazon / Hobart data centers

Lake County (Hobart)

AWS is the announced operator/end user of the campus, tied to a $15 billion Amazon investment in Hobart.

Key data: Amazon Web Services

CORROBORATED

Limitation: Tracker-sourced investment figure.

Open source →

POWER SUPPLIER

Amazon / Hobart data centers

Lake County (Hobart)

NIPSCO will supply the campus, ramping to 2,400 MW by end-2032 with service starting 2027; IURC Cause No. 46322 approved the NIPSCO–Amazon special contract and a NIPSCO–GenCo PPA, and MISO Project 51141 covers a 1,500 MW "New Hobart Load Addition."

Key data: NIPSCO; IURC Cause No. 46322; MISO Project 51141; 2,400 MW by 2032

VERIFIED PRIMARY

Limitation: Repository is a community-maintained aggregation of primary filings; docket numbers not independently re-fetched from IURC/MISO this session.

Open source →

WATER SUPPLIER

Amazon / Hobart data centers

Lake County (Hobart)

NOT_FOUND for a named water utility. The developer told the plan commission the buildings "would not need water"; a tracker estimates ~14 million gallons/year for water-based cooling.

Key data: No supplier named; ~14 M gal/yr (tracker estimate)

DISCOVERY LEAD

Limitation: City of Hobart utilities role not documented in fetched sources.

Open source →

JURISDICTION STACK

Amazon / Hobart data centers

Lake County (Hobart)

The City of Hobart controls zoning (Plan Commission, City Council, Board of Public Works and Safety); state/federal authorities include IURC, MISO, IDEM and USACE; the site is in Lake County.

Key data: City of Hobart (Plan Commission, Council, BPW); IURC; MISO; IDEM; USACE

CORROBORATED

Limitation: n.a.

Open source →

PLANNING ZONING CONTACT

Amazon / Hobart data centers

Lake County (Hobart)

Authority rests with the Hobart Plan Commission; the city's published directory gives the Planning & Zoning Department phone but no named case manager for this project.

Key data: City of Hobart Planning & Zoning / Plan Commission, 414 Main St., Hobart, IN 46342 — 219-942-7985

VERIFIED PRIMARY

Limitation: No named planner or email published for the data-center cases.

Open source →

ECON DEV CONTACT

Amazon / Hobart data centers

Lake County (Hobart)

The city publishes an Economic Development phone line in its staff directory; no named individual tied to the Amazon project was found.

Key data: City of Hobart Economic Development — 219-942-5517

VERIFIED PRIMARY

Limitation: No county-level (Lake County) EDC contact found for this project.

Open source →

GENERAL CONTACT

Amazon / Hobart data centers

Lake County (Hobart)

NOT_FOUND for a project-specific PIO or company community-relations contact; the general city permitting numbers are the only channels identified (Building 219-942-1722, Zoning 219-942-7985).

Key data: City of Hobart Building Dept. 219-942-1722

CORROBORATED

Limitation: Amazon side contact not published in fetched sources.

Open source →

SURROUNDING INFRASTRUCTURE

Amazon / Hobart data centers

Lake County (Hobart)

Records reference a New Hobart 345 kV load addition and related transmission/generation, gas-fired generation and battery storage; a tracker puts the nearest 345 kV line ~0.7 mi away and Sprout Ditch ~0.9 mi; the Hobart Board of Works adopted a construction traffic plan.

Key data: New Hobart 345 kV load addition; 345 kV line ~0.7 mi; Sprout Ditch

CORROBORATED

Limitation: Water/sewer trunk lines and fiber routes not documented.

Open source →

EXACT LOCATION

Sabey Decatur Technology Park (2025-CAP-856 / 2025-CVR-856)

Marion County (Indianapolis, Decatur Twp)

The ~130-acre site is at the northeast corner/intersection of Kentucky Avenue (SR-67) and Camby Road in Decatur Township, inside the existing industrially zoned Decatur Technology Park, directly across from an AES substation.

Key data: Kentucky Ave (SR-67) & Camby Road, Decatur Township, Indianapolis; ~130 acres

CORROBORATED

Limitation: No street number or parcel ID published; project site plan uses access from SR-67 and Camby Road.

Open source →

OWNERSHIP CHAIN

Sabey Decatur Technology Park

Marion County

The petitioner is Sabey Data Center Properties LLC, a division of Seattle-based Sabey Corporation; Sabey Data Centers is jointly owned by Sabey Corporation and institutional clients managed by National Real Estate Advisors (some accounts affiliated with the IBEW).

Key data: Sabey Data Center Properties LLC → Sabey Corporation + National Real Estate Advisors-managed clients

VERIFIED PRIMARY

Limitation: Land-title holder for the 130 acres not identified in fetched sources.

Open source →

OPERATOR

Sabey Decatur Technology Park

Marion County

Sabey designs, builds and operates its data centers; the Decatur facility is a colocation project intended to lease space to multiple tenants, with no tenant named.

Key data: Sabey Data Centers (operator); colocation, tenants unnamed

CORROBORATED

Limitation: n.a.

Open source →

POWER SUPPLIER

Sabey Decatur Technology Park

Marion County

AES Indiana is the electric supplier; the plan includes a 10-acre on-site substation ramping to 250 MW over five years, with initial utility upgrades anticipated by Q4 2027 and Sabey funding transmission/distribution costs.

Key data: AES Indiana; 10-acre substation; 250 MW over 5 years

VERIFIED PRIMARY

Limitation: No IURC cause number or special contract ID published.

Open source →

WATER SUPPLIER

Sabey Decatur Technology Park

Marion County

The project website names Citizens Water as supplier, with a closed-loop design requiring a one-time 1,000,000-gallon fill (500,000 gal per building, 2028 and 2030) and 200,000–300,000 gallons/year ongoing.

Key data: Citizens Water (Citizens Energy Group); 1.0 M gal initial fill; 200–300k gal/yr

VERIFIED PRIMARY

Limitation: Developer-published figures; no service agreement number.

Open source →

JURISDICTION STACK

Sabey Decatur Technology Park

Marion County

Land-use authority is the consolidated City of Indianapolis/Marion County Metropolitan Development Commission (with hearing examiner) covering Decatur Township; IURC governs utility investment; litigation is pending in Marion Superior Court.

Key data: Metropolitan Development Commission (MDC) + hearing examiner; Decatur Township; IURC; Marion Superior Court

CORROBORATED

Limitation: City-County Council did not vote on the variance.

Open source →

PLANNING ZONING CONTACT

Sabey Decatur Technology Park

Marion County

The MDC hearing examiner who recommended approval is named, as are counsel for both sides.

Key data: Judy Weerts Hall, MDC Hearing Examiner; Mindy Westrick Brown (Sabey counsel); Laureen White (residents' counsel)

CORROBORATED

Limitation: No department phone/email captured for the case file.

Open source →

ECON DEV CONTACT

Sabey Decatur Technology Park

Marion County

Indy Economic Development Inc. (with prior Indy Chamber endorsement) backs the project and is working with Sabey on a tax abatement; a spokesperson and attorney are named in coverage.

Key data: Indy Economic Development Inc.; spokesperson Aliya Wishner; attorney Doug Brown

CORROBORATED

Limitation: Roles/titles partially garbled in source text; no direct contact details.

Open source →

GENERAL CONTACT

Sabey Decatur Technology Park

Marion County

The project website states a dedicated community liaison exists for inquiries, but no name, phone or email was published on the fetched page.

Key data: Community liaison referenced, unnamed

DISCOVERY LEAD

Limitation: NOT_FOUND for an actual phone/email; legal notices are posted separately as PDFs.

Open source →

SURROUNDING INFRASTRUCTURE

Sabey Decatur Technology Park

Marion County

An AES substation sits across the street, a 10-acre substation is planned on site, access is from SR-67/Kentucky Avenue and Camby Road with 200-foot residential buffers; nearest 345 kV line ~1.1 mi and Seerley Creek ~1.0 mi.

Key data: AES substation across street; 345 kV ~1.1 mi; Seerley Creek ~1.0 mi

CORROBORATED

Limitation: Fiber and sewer trunk detail not documented.

Open source →

EXACT LOCATION

Metrobloks (tax abatements 2026-A-016/017)

Marion County (Indianapolis, Martindale-Brightwood)

The site is the ~14-acre former Sherman Drive-In theater property in Martindale-Brightwood, vacant since 1983.

Key data: 2505 N. Sherman Drive, Indianapolis; ~13–14 acres

CORROBORATED

Limitation: No parcel ID published; address sometimes given as "N. Sherman Ave."

Open source →

OWNERSHIP CHAIN

Metrobloks

Marion County

NOT_FOUND. Fetched trade coverage, trackers, local reporting and metrobloks.com (which returned no usable content) — no land owner, parent company or registered agent for Metrobloks' Indianapolis entity was published.

Key data: n.a. (developer Metrobloks; CEO named Ernest/Earnest Popescu)

DISCOVERY LEAD

Limitation: Company website content not extractable; CEO name spelled inconsistently across sources.

Open source →

OPERATOR

Metrobloks

Marion County

Metrobloks is described as both developer and operator of the metro-edge AI-ready facility (site code IND A1), 72–75 MW at buildout.

Key data: Metrobloks (IND A1); 72–75 MW

CORROBORATED

Limitation: No tenant named.

Open source →

POWER SUPPLIER

Metrobloks

Marion County

Public radio reporting states the facility would draw electricity through contracts with AES Indiana rather than from the residential grid.

Key data: AES Indiana (contracted supply)

CORROBORATED

Limitation: No contract ID or IURC cause number published.

Open source →

WATER SUPPLIER

Metrobloks

Marion County

A closed-loop cooling system is planned: ~19,000 gallons to fill the first building and ~47,500 gallons for the second, recirculated rather than consumed. No water utility is named.

Key data: ~19,000 gal (bldg 1) + ~47,500 gal (bldg 2), closed loop

CORROBORATED

Limitation: Supplier name NOT_FOUND (Citizens Energy Group not confirmed for this site).

Open source →

JURISDICTION STACK

Metrobloks

Marion County

The Metropolitan Development Commission approved the rezoning (April/May 2026) and the City-County Council was engaged on the project and on a temporary stay for high-impact data centers; the site is in Indianapolis/Marion County.

Key data: MDC; Indianapolis City-County Council; Marion County

CORROBORATED

Limitation: Tax abatement cases 2026-A-016/017 were not directly fetched this session.

Open source →

PLANNING ZONING CONTACT / ECON DEV CONTACT

Metrobloks

Marion County

NOT_FOUND for named staff. Coverage identifies the MDC as the deciding body and City-County Councilor Ron Gibson as the area representative, but no planner, case manager or economic-development officer was named for this project.

Key data: Councilor Ron Gibson (district representative)

DISCOVERY LEAD

Limitation: Abatement petitions handled through Indianapolis DMD; staff not named in fetched sources.

Open source →

GENERAL CONTACT

Metrobloks

Marion County

NOT_FOUND. The only project-side contact identified is the CEO by name; reporters noted Metrobloks did not respond to email inquiries and the corporate site returned no extractable contact information.

Key data: Metrobloks CEO Ernest Popescu (no phone/email published)

DISCOVERY LEAD

Limitation: metrobloks.com and /about-us returned no content on fetch.

Open source →

SURROUNDING INFRASTRUCTURE

Metrobloks

Marion County

The site is a decades-vacant brownfield at 25th Street and Sherman Drive; a company-aligned listing notes it is less than 4.7 miles from the FD-IX Internet Exchange Point with ~0.21 ms latency and carrier-neutral connectivity.

Key data: FD-IX Internet Exchange <4.7 mi; 25th St & Sherman Dr

CORROBORATED

Limitation: Substation/transmission and sewer detail not published.

Open source →

EXACT LOCATION

Blue Power LLC

Clay County (near Brazil / Carbon)

Permit documents show four adjoining plats totaling 27.62 acres off East County Road 1350 North just south of Carbon, with Brazil listed as the mailing city.

Key data: 4 plats, 27.62 acres, E. CR 1350 N, south of Carbon (Brazil, IN)

CORROBORATED

Limitation: Permit itself not fetched directly; no parcel IDs.

Open source →

OWNERSHIP CHAIN

Blue Power LLC

Clay County

Blue Power LLC owns the four adjoining plats and is the renamed successor of Claybridge Energy LLC, previously Midwest Gas Storage, Inc.; its CEO is Illinois-based Terry O'Malley.

Key data: Blue Power LLC (formerly Claybridge Energy LLC, formerly Midwest Gas Storage, Inc.); CEO Terry O'Malley

CORROBORATED

Limitation: Ultimate beneficial owner/parent above Blue Power LLC not identified; no Secretary of State filing fetched.

Open source →

OPERATOR

Blue Power LLC

Clay County

NOT_FOUND. The data-center user is unidentified: Blue Power's IDEM permit covers a combined-cycle power plant that would provide dedicated power to a nearby data center, but no data-center operator has been disclosed.

Key data: Data center operator undisclosed

DISCOVERY LEAD

Limitation: Project is disclosed only through the power-plant permit.

Open source →

POWER SUPPLIER

Blue Power LLC

Clay County

Power would come from Blue Power's own behind-the-meter combined-cycle plant rather than a named utility; a tracker lists WVPA / Parke County REMC as grid context and 400 MW capacity.

Key data: Self-supply via Blue Power combined-cycle plant; tracker: WVPA/Parke County REMC, 400 MW

DISCOVERY LEAD

Limitation: Utility attribution is tracker-sourced and unconfirmed; no interconnection/docket reference found.

Open source →

WATER SUPPLIER

Blue Power LLC

Clay County

NOT_FOUND. Searched IDEM-related coverage and county meeting reporting; no water utility, well field or agreement has been disclosed for the Clay County project.

Key data: n.a.

DISCOVERY LEAD

Limitation: n.a.

Open source →

JURISDICTION STACK

Blue Power LLC

Clay County

IDEM's Office of Air Quality issued the significant source modification permit; Clay County Commissioners and County Council are the local bodies, but the county has no zoning laws and says it cannot impose a moratorium; IDNR was cited as another avenue for residents.

Key data: IDEM OAQ; Clay County Commissioners & Council (no county zoning); IDNR

CORROBORATED

Limitation: The absence of county zoning is a key jurisdictional gap.

Open source →

PLANNING ZONING CONTACT

Blue Power LLC

Clay County

NOT_FOUND (structurally): Clay County has no zoning ordinance, so no planning/zoning case authority exists. Permit paperwork listed local officials as notified contacts, with a reported email/phone mismatch.

Key data: Listed officials: Patricia Heffner (Brazil Council At-Large), Mayor Brian Wyndham, Commissioner Bryan Allender

CORROBORATED

Limitation: Reporting notes the contact email/phone listed for one official actually belonged to a different person (Shane Litz).

Open source →

ECON DEV CONTACT / GENERAL CONTACT

Blue Power LLC

Clay County

NOT_FOUND. Searched for a Clay County economic development contact and any company contact; only the CEO's name was published, and the county announcements page returned no relevant content.

Key data: n.a.

DISCOVERY LEAD

Limitation: No EDC or PIO identified for this project.

Open source →

SURROUNDING INFRASTRUCTURE

Blue Power LLC

Clay County

NOT_FOUND for detailed infrastructure. The only located context is the site's position south of Carbon off E. CR 1350 N on former gas-storage land (Midwest Gas Storage lineage), implying gas infrastructure.

Key data: E. CR 1350 N; former gas-storage site lineage

DISCOVERY LEAD

Limitation: No substation, pipeline, water/sewer or fiber specifics published.

Open source →

Indiana project / topic roster

Research currently compiled for Indiana

44 project/topic labels are retained here, including unresolved aliases that still require canonical reconciliation.

Project or topicEvidence state
Amazon / Hobart air permit applicationSource-backed / reconciliation-aware
Amazon / Hobart campusSource-backed / reconciliation-aware
Amazon / Hobart data center campusSource-backed / reconciliation-aware
Amazon / Hobart data centersSource-backed / reconciliation-aware
Amazon / Hobart data centers (permit 089-50590-00739, 782 generators)Source-backed / reconciliation-aware
Amazon / Hobart — incentives and paymentsSource-backed / reconciliation-aware
Amazon / Hobart — ratepayer treatmentSource-backed / reconciliation-aware
Amazon / Hobart — traffic planSource-backed / reconciliation-aware
Amazon Data ServicesSource-backed / reconciliation-aware
Amazon Data Services (NPDES/air permit 141-50312-00650)Source-backed / reconciliation-aware
Amazon Data Services New CarlisleSource-backed / reconciliation-aware
Amazon Data Services — Section 401 certificationSource-backed / reconciliation-aware
Amazon Data Services — air permit modification 141-50312-00650Source-backed / reconciliation-aware
Amazon Data Services, Inc. facility (New Carlisle area, per IDEM public-notice listing by county)Source-backed / reconciliation-aware
Blue Power LLCSource-backed / reconciliation-aware
Countywide data center moratoriumSource-backed / reconciliation-aware
Data center at 2505 North Sherman Drive, Council District #8Source-backed / reconciliation-aware
Decatur Technology Park data center — various addresses 6700–8210 Camby Rd & 6600–6833 Kentucky Ave; East Building A and West Building BSource-backed / reconciliation-aware
IURC Cause No. 46097 — I&M large load tariffSource-backed / reconciliation-aware
Indiana data center sales tax exemptionSource-backed / reconciliation-aware
MetrobloksSource-backed / reconciliation-aware
Metrobloks (tax abatements 2026-A-016/017)Source-backed / reconciliation-aware
Metrobloks abatementsSource-backed / reconciliation-aware
Metrobloks abatements 2026-A-016 / 017Source-backed / reconciliation-aware
NIPSCO GenCo, IURC Cause 46183Source-backed / reconciliation-aware
NIPSCO large-load sub-docketSource-backed / reconciliation-aware
NOT_FOUND — DECOMMISSIONING_PROVISION for IN anchor projectsSource-backed / reconciliation-aware
NOT_FOUND — quantitative EJ screening for IN sitesSource-backed / reconciliation-aware
New stationary data center at 1598 W SR 42, Mooresville, IN 46158 (Woodland Caribou LLC)Source-backed / reconciliation-aware
Power generation project associated with a potential data center development, 499 E CR 1350 N, Brazil, IN 47834Source-backed / reconciliation-aware
Project Louie (Google)Source-backed / reconciliation-aware
Project Louie (Google) — AES Indiana agreementSource-backed / reconciliation-aware
Project Louie (Google) — abatementSource-backed / reconciliation-aware
Project Louie PUD conditionsSource-backed / reconciliation-aware
Proposed SU-47 noise and setback standardsSource-backed / reconciliation-aware
Proposed SU-47 special use districtSource-backed / reconciliation-aware
Sabey Decatur Technology ParkSource-backed / reconciliation-aware
Sabey Decatur Technology Park (2025-CAP-856 / 2025-CVR-856)Source-backed / reconciliation-aware
Sabey — AES Indiana rate impactSource-backed / reconciliation-aware
Statewide moratorium demandSource-backed / reconciliation-aware
Two adjacent Hobart data center sites treated as one source (26 buildings)Source-backed / reconciliation-aware
Woodland Caribou LLC / Project Louie (Google)Source-backed / reconciliation-aware
Woodland Caribou LLC data centerSource-backed / reconciliation-aware
Woodland Caribou LLC data center (permit T109-50085-00094)Source-backed / reconciliation-aware
Research and local discovery

Find data center projects and the public records around them in Indiana.

This state page combines mapped locations with permits, planning and zoning activity, infrastructure context, operators and civic records. The deeper corpus is supplemented by 7 accepted rows from the validated national refresh. Counts describe evidence records, not unique facilities.

Where a source does not establish a location, utility, water supplier or other fact, that gap remains explicit rather than being converted into an unsupported map point or claim.

See the evidence and publication methodology →

Indiana Data Centers, Projects & Compute Infrastructure Research | Compute Equity Atlas